All very reasonable. Until the apparatus is well understood all tests
will be pulsed, meaning CW inhibit = ON. I'll start on estimates of
beam loss and heating for the more general CW case, following
calculations Bob Michaels provided for our target, calculations I did
for Moller foil ~years ago and discussing with Danny/Pavel if thermal
analysis can be done.
On 11/08/2011 11:35 AM, Alexandre Camsonne wrote:
> Yes that sounds very reasonable. We don't want to mess up the machine
> at its starts
>
> Actually don't we need an OSP or TOSP too before we can put beam in
> the device ? There is a lot of new things there. I think we usually do
> that in the halls not sure on the accelerator side.
>
> Alexandre
>
>
>
> On Tue, Nov 8, 2011 at 11:22 AM, Matt Poelker<poelker at jlab.org> wrote:
>> On the subject of "check out with electron beam", I am going to require
>> you to write a test plan, and to have it reviewed by knowledgeable Ops
>> staff, like Mike Spata, Jay Benesch, Geoff Krafft and/or Mike
>> Tiefenback. The obvious big concern here....how do you plan to avoid
>> burning a hole in the exit foil downstream of the spectrometer? and if
>> you do burn a hole in the exit window, what are the expected consequences?
>> Matt
>>
>>
>> Joseph Grames wrote:
>>> Dear PEPPo Collaborator,
>>>
>>> We will meet tomorrow Wednesday 11/9 at 10:30EST, locally in ARC428
>>> and by call-in is 757-269-6121.
>>>
>>> Eric& I would like to discuss two topics:
>>>
>>> *System Readiness* - please post your punchlist of remaining tasks
>>> necessary to complete your system to the wiki, meaning all the steps
>>> you envision before we are in a position to use/test your system with
>>> beam. This should include hardware, software, procedures,
>>> documentation, cables, labels, jobs in the service building, jobs in
>>> the tunnel. Anything you can envision.
>>>
>>> == (WIKI) ==> https://positron.jlab.org/wiki/index.php/November_9%2C_2011
>>>
>>> *Check-out with electron beam* - please prepare a straw man for the
>>> first test you would like to perform with 6.3 MeV electron beam,
>>> meaning who will/can do the test, prerequisites, clock hours needed,
>>> possible accesses needed, range of beam current or polarization,
>>> hardware/software configurations. Beam tests plans should be
>>> submitted using ATLIS (go to web site, login, choose create, pick a
>>> title beginning with "PEPPO:", fill in the blanks the best you can).
>>> If offsite then use proxy to access web site.
>>>
>>> == (ATLIS) ==> http://opsweb.acc.jlab.org/CSUEApps/atlis/atlis.php
>>>
>>>
>>>
>>> ------------------------------------------------------------------------
>>>
>>> _______________________________________________
>>> PEPPo mailing list
>>> PEPPo at jlab.org
>>> https://mailman.jlab.org/mailman/listinfo/peppo
>>>
>>
>> --
>> Matt Poelker
>> Jefferson Lab
>> MS Bldg 5A, Rm 500-17
>> 12000 Jefferson Ave.,
>> Newport News, VA 23606
>> poelker at jlab.org
>> 757-269-7357 office
>> 757-584-7357 pager
>>
>>
>> _______________________________________________
>> PEPPo mailing list
>> PEPPo at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/peppo
>>
More information about the PEPPo
mailing list