Dear PEPPo Collaborator,
Although subject to change we should plan for ~8 hours of beam studies
this Thursday beginning sometime shortly after ~9am.
*Sue *- please let me know if you would like an iteration of working on
the PEPPo collimator software. if yes, we just need to coordinate a
reasonable time slot because other beam tests depend upon "using as-is"
the collimators, at least to retract them out of the way.
*Scott *- if you find yourself ready this week to implement any of the
magnet wrappers this could be coordinated; if not, I will lobby for time
~next week.
*Erica/Riad/Eric* - we should discuss by Wed the daq status and agree on
the sequence of tests; ideally we put the daq through as many conditions
as possible, and measure at compton at least pita induced charge
asymmetry, maybe a physics related asymmetry; we can collect background
data too
*myself *- i will focus on testing various run conditions that help us
prepare for experiment: higher beam current on target foil, changing
beam energy, understanding position of spectrometer viewer
-Joe
-------- Original Message --------
Subject: [PEPPo] Beam Studies for Next Thursday
Date: Fri, 13 Apr 2012 11:06:46 -0400
From: Arne Freyberger <freyberg at jlab.org>
To: bteam at jlab.org, peppo at jlab.org, Fulvia Pilat <pilat at jlab.org>, Mary
Logue <logue at jlab.org>, Andrew Hutton <andrew at jlab.org>
Expect to hear about a possible change to the schedule that will impact
the pass configuration after the Energy change on Thursday.
Specifically, the C100 folks should prepare for high current 3-pass
running to Hall-C from April 20th to April 26ish. This beam loading
environment was to occur during the last six days of the run, but
Physics is considering moving it up. This news might alter the
proposed Beam studies plan below. The number of hours in the Beam
Studies bank is 19.
Arne
2 This Week \\ 2012-04-19
2.1 This Week \\ 2012-04-19 Thursday
Scheduled Tasks Expected Actual Campaign Beam
Duration
Termination
(h)
Initial fOpts/Allsaves 0.5
Program A & B & C
Hall I to V test
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12286> 0.5
Misc A dumplette
C100 test(4) <http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12297> 7.5
C100 Inj
2l25-5 PZT tuner
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12314> 0.5
C100 Inj
A_Q Compton Test <http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12299> 3
PEPPo Inj
e^+ on FC <http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12300> 2
PEPPo Inj
Shielding work <http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12233> 2
PEPPo Inj
Collimator Cntr upgrade
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12315> 1.0
PEPPo Inj
Restoration 0.0 0 Program A & B & C
Parasitic Hours -8
Total 9.0
Test Hall-B Halo Measurements
<http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12254> is to be
scheduled when Hall-B is not taking beam waiting during HD-ICE target
NMR measurement periods
3 Next Week \\ 2012-04-25 Wed
3.1 Preliminary Beam Studies Program \\ Next Week: 2012-04-25 Wed
Beam Studies will be finalize at Friday 9am MCC Beam Studies Scheduling
meeting.
.
.
C100!
Date: $\today$
Author: Arne Freyberger
Org version 7.5 with Emacs version 23
Validate XHTML 1.0 <http://validator.w3.org/check?uri=referer>
--
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab Office: (757) 269-6268
12000 Jefferson Avenue Cell: (757) 876-6289
Newport News, VA 23606 Email: freyberg at jlab.org
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/peppo/attachments/20120416/515a4ca1/attachment.html
-------------- next part --------------
An embedded and charset-unspecified text was scrubbed...
Name: file:///C|/DOCUME%7E1/GRAMES/LOCALS%7E1/TEMP/nsmail.txt
Url: https://mailman.jlab.org/pipermail/peppo/attachments/20120416/515a4ca1/attachment.txt
More information about the PEPPo
mailing list