[PEPPo] Beam Studies Wednesday Feb 22nd
Paul Gueye
gueye at jlab.org
Wed Feb 22 02:31:49 EST 2012
Hi Joe,
I will not be there after 12:00 because I have classes to teach. I freed-up my Wednesday mornings (unless there are impromptu meetings) and Thursdays. Leke will be there to do the tests.
Paul
On Feb 21, 2012, at 20:38 13, Joe Grames wrote:
> Dear PEPPo Collaborators,
>
> Over the last week the control chassis for the high current power supplies was removed for improvements. It has since been tested, except with the spectrometer magnet. So this remains to be done tomorrow before we begin our tests. I will do my best to execute the plan below, but keep in mind nearly all of the tests are contingent on recommissioning the control chassis first.
>
> Rather than working in the back of the room, how about we setup at two consoles up front; one for beam controls and one for data acquisition. We should view each of our beam studies as a cross training opportunity, soaking up as much as possible about how your experiment works.
>
> Please show up early enough to check out your system.
>
> 1100 - 1200
> Recommission MPD5D03
> 1200 - 1400
> Restore beam to PEPPo FCUP
> HCO ITV5D03 and 5 new magnets
> PEPPo cup ItoV at scope or DAQ
> Rates at Compton Polarimter
> Test Fiber Array
> Test Annihilation Detector
>
> _______________________________________________
> PEPPo mailing list
> PEPPo at jlab.org
> https://mailman.jlab.org/mailman/listinfo/peppo
--
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
Paul Gueye
* Hampton University
Physics Department - 102E
Hampton, VA 23668
W: (757) 727-5542
F: (757) 728-6910
E: paul.gueye at hamptonu.edu
* Jefferson Lab
Physics Division - F382
12000, Jefferson Avenue
Newport News, VA 23606
W: (757) 269-6287
E: gueye at jlab.org
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/peppo/attachments/20120222/de2f7e79/attachment.html
More information about the PEPPo
mailing list