[Prex] Hall A readiness; sweep planned; RC meeting
Robert Michaels
rom at jlab.org
Wed Aug 5 09:58:36 EDT 2020
Today, I told the PD and Radcon that we can sweep the hall A at any time that is convenient, then
we go to controlled access. I don't think we need that many keys for the bit of work that remains.
If Radcon needs a person to help with the sweep we can coordinate that. *If* the hall B gets beam
today, then we could get beam in hall A tomorrow. Big *if*. Stay tuned. Will know more after
the 1:30 MCC meeting.
* Hall A techs have done their checklist => hall is ready for beam, magnets work, etc
* Victoria will ramp up the magnets to nominal 2.2 GeV settings today.
* Devi and Bogdan continue to test R-HRS detectors. Looks pretty good so far.
* Chuck Long appears to have fixed the ArCO2 leak.
* I don't think there are any other problems (let me know if I'm wrong).
* I think Cameron is done with his DAQ repairs/tests but I guess we'll hear at the 3:30 RC meeting
And the RC meeting is here at 3:30
https://bluejeans.com/178990432
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/prex/attachments/20200805/b5f56526/attachment.html>
More information about the Prex
mailing list