[Prex] [New Logentry] RC report
chandan at jlab.org
chandan at jlab.org
Sat Aug 8 11:35:01 EDT 2020
Logentry Text:
--
Hall A hasn't received any beam so far.
MCC will push high current for hall C and then they will start extracting the first pass beam for hall A.
With 300 microAmp current in the machine, Hall A may get up to 70 microAmp current (with full current into other halls) over the weekend.
There will be some RF work on the coming Tuesday and that may take about a shift.
If you have any plan to work in the hall, please make a plan and let RC know about that.
Since we may not get high current beam over the weekend, we should have a plan to utilize the low current beam as much as possible.
So, we will have a short RC meeting at 3:30 PM today to discuss the plan.
Bluejeans link : https://bluejeans.com/256205934
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3822584
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/prex/attachments/20200808/c56d5f7b/attachment.html>
More information about the Prex
mailing list