Dear all

Yesterday day through swing we took production data on ND3+. Late swing around 11pm 1L06 dropped HV and the machine was down through owl. 
Thirty minutes ago around 8am, beam became available. No optics were changed and a careful straight to FCup was performed. We are now back to production data taking.

There had been a maintenance day planned but the PD called at 3:30am to inform me that it was cancelled. Given the success of finally being able to deliver 75-80 mA to Hall-C and given the considerable downtime over the last couple of days, they decided to maintain beam delivery.

We will have the RC meeting at 2pm to discuss plans for the maintenance period and the next few days. Stephen Bueltmann will be the next RC.

Link for our RC meeting of today (the usual one):
https://jlab-org.zoomgov.com/j/1608674253?pwd=SFZyYmZLWXJieGtpV2dEdVRiUEJnUT09 <https://jlab-org.zoomgov.com/j/1608674253?pwd=SFZyYmZLWXJieGtpV2dEdVRiUEJnUT09>
Passcode: 786506 

Regards
Bryan
RC 

___________________________________

Dr. Bryan McKinnon

Nuclear and Hadron Physics Research
School of Physics and Astronomy
University of Glasgow
Glasgow
G12 8QQ
Scotland UK

Tel: (+44/0) 141-330-7226
___________________________________

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/rgc/attachments/20220803/b71ea206/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: smime.p7s
Type: application/pkcs7-signature
Size: 1927 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/rgc/attachments/20220803/b71ea206/attachment.p7s>


More information about the Rgc mailing list