We are continuing our program of working on the SBS magnet during day shift and switching over to taking beam on swing and owl. The details are below:
Accelerator as Related to Hall A
- On day shift they are resuming work to resolve the issue with the
FSD fiber that prevented beam from being delivered to the Hall last night
Plan for Tue Day Shift [08:00--16:00]
- Hall is in Controlled Access. No sweep was required because beam was not delivered to the Hall
last night.
- Jessie and his team are implementing the fixes on the SBS magnet
The team is 5 people, and they have priority
- Other requested accesses to the hall:
- GEM and GRINCH gas work (Jack)
- Checking GEM low voltage connections (H. Szumila-Vance, E. Wertz)
- Moller magnet temperature sensors (S. Malace and E. Becker)
- SBS and LHRS beam line signal investigations (P. King and D. Flay)
We have only 10 keys for access to the hall, so we'll manage the work so
we don't try to do everything at the same time.
Plan for Tue Swing Shift [16:00--23:59]
- Take beam when available and start our commissioning program.
We will start with beam centering with the BigBite magnet off,
and then turn on the magnet and check the beam centering.
If all goes well, we switch over to our optics program.
Commissioning Plan: https://sbs.jlab.org/wiki/index.php/CommissioningPlan
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3922724
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sbs/attachments/20211012/33e8019c/attachment.html>
More information about the Sbs
mailing list