Here is the list of tasks needed to install the UV layer in the hall.
Barring any unforeseen issues the layer swap should happen on *January 6th*.
I have also attached a picture below where you can see the state of the UV
layer. It has everything ready except for the APVs, which will be taken out
of the hall on January 3rd.
Schedule Parallel Task 1 Parallel Task 2
1/3/2022 Put 3-slot BPs in UV layers in BB
Move UV to the test lab and set up HDMI cables
1/4/2022 Pedestal and comsic test on UV layer
1/5/2022 Resolve any issues
1/6/2022 Swap J0 with the UV layer
1/7/2022 Resolve any issues
1/8/2022 Weekend
1/9/2022 Weekend
1/10/2022 Resolve any issues
Best,
Sean
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sbs_gems/attachments/20211222/e9835a1a/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: UV_Prod1.jpg
Type: image/jpeg
Size: 3006418 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/sbs_gems/attachments/20211222/e9835a1a/attachment-0001.jpg>
More information about the Sbs_gems
mailing list