HI Sean
Thanks for sending out the plan.
I would like to add one more thing:
here at UVa we have built the new HV divider boards with the resistance 3 times smaller than those on the UV chambers right now. These HV boards will significantly reduced the gain drop issue, and the efficiency for the UV chambers will stay close to 90% during production. One question is whether pedestal noise would go up.
Vimukthi and Huong are starting to test these boards. They plan to get them fully tested using high intensity x-rays by January 5, or earlier.
If everything looks good by then, I suggest we replace the HV board of UV layer 4 before it is installed.
We can replace the boards of the other 3 layers, while they are in the stack.
Best
Nilanga
________________________________
From: Sbs_gems <sbs_gems-bounces at jlab.org> on behalf of Sean Jeffas <sj9ry at virginia.edu>
Sent: Wednesday, December 22, 2021 8:46 AM
To: Sbs_gems at jlab.org <sbs_gems at jlab.org>
Subject: [Sbs_gems] [EXTERNAL] UV Layer 4 installation update
Hi All,
Here is the list of tasks needed to install the UV layer in the hall. Barring any unforeseen issues the layer swap should happen on January 6th. I have also attached a picture below where you can see the state of the UV layer. It has everything ready except for the APVs, which will be taken out of the hall on January 3rd.
Schedule Parallel Task 1 Parallel Task 2
1/3/2022 Put 3-slot BPs in UV layers in BB
Move UV to the test lab and set up HDMI cables
1/4/2022 Pedestal and comsic test on UV layer
1/5/2022 Resolve any issues
1/6/2022 Swap J0 with the UV layer
1/7/2022 Resolve any issues
1/8/2022 Weekend
1/9/2022 Weekend
1/10/2022 Resolve any issues
Best,
Sean
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sbs_gems/attachments/20211222/4e045365/attachment.html>
More information about the Sbs_gems
mailing list