Hello Team PPU,
See the update from the Project Director.
Cheers,
Ed
________________________________
From: Galambos, John D. <galambosjd at ornl.gov>
Sent: Friday, October 7, 2022 11:32 AM
To: Andersen, Ken <andersenkh at ornl.gov>
Cc: Ed Daly <edaly at jlab.org>; Cain, Wendy <cainwa at ornl.gov>
Subject: [EXTERNAL] PPU weekly update
There was a concerted PPU effort this week to prepare equipment for the power ramp-up. The 2 cryomodules installed in the tunnel underwent tests prior to the planned cooldown next week. In the klystron galley, the high-power convertor modulator was run at required duty factor and voltage. Also, the first fully integrated RF production including high voltage systems, convertor modulators, RF transmitters, klystrons, with appropriate interlocks was accomplished. RF power was produced in 5 klystrons. The planned power ramp-up starting in November is presently on schedule. Other installation activities proceeded in the klystron gallery and tunnel for future ramp-up phases, including cable terminations and wave guide installation.
John Galambos
Proton Power Upgrade Project Director
865.576.5482
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sns_ppu_group/attachments/20221007/4930c6b4/attachment.html>
More information about the Sns_ppu_group
mailing list