[Sns_ppu_group] Fw: PPU weekly update
Ed Daly
edaly at jlab.org
Mon Oct 17 08:45:21 EDT 2022
Hi Team PPU,
FYI from the project director.
-Ed
________________________________
From: Galambos, John D. <galambosjd at ornl.gov>
Sent: Friday, October 14, 2022 3:30 PM
To: Andersen, Ken <andersenkh at ornl.gov>
Cc: Cain, Wendy <cainwa at ornl.gov>; Ed Daly <edaly at jlab.org>
Subject: [EXTERNAL] PPU weekly update
This week PPU activities focused on preparing for the upcoming initial power ramp-up phase. In the superconducting area, cryomodules 5 and 6 are at the final assembly stage at JLab, awaiting return end cans. JLab visited the end can vendor this week, and SNS is repairing an end can at ORNL. In the RF area system checkouts continued on the installed equipment for the upcoming ramp-up phase. RF circulators and transmitter tanks needed for the next ramp-up phases were also received. In the Ring area, at FNAL the first new injection magnet measurements began this week. Installation activities proceeded in the tunnel and klystron gallery for equipment needed in the next phase of the power ramp-up. Also, vendor outreach was initiated for the RTBT stub construction.
John Galambos
Proton Power Upgrade Project Director
Mobile: 865-228-1531 office: 865-576-5482
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sns_ppu_group/attachments/20221017/9d36518b/attachment.html>
More information about the Sns_ppu_group
mailing list