this is the status and report of the BONuS experiment (Run Group F), Friday 20th, 2020.
* early in the morning the Accelertor Ops finished the calibration of the BPMs
* finished small tasks in the hall
* checking of gas leaks and set bubblers levels
* bubbler camera
* RadCon Survey of RTPC 1 and instructions how to translate it to EEL 125
* Final checks from Dan C., Yuri G. and Stepan S.
* We were ready for Hall Sweep at 12:15 (one hour over my estimation). Started at 12:40, finished at 13:10.
* During the sweep Eugene P. proceed to ramp up the magnets (4T solenoid, 20kG Torus)
* Harp scans at tagger started at 14:50 due to issues with the injector.
* Tagger degaussed ~14:50 and started to fine tuning beam at Faraday cup (2H01 and 2C24), finished ~17:30
* BOM not working (Nathan B. notified)
* Beam position by Halo Counters (2C24): X: 0.1mm Y: -0.4mm
* In the meanwhile target was filled with D2 (Sebastian) and RTPC always flowing with pre-mix gas.
* no visible bubbles, but apparently everything in order
* 17:35 ready for production. 240 nA, Target 65psig of D2.
* MCC called for interruption of the beam ~17:50 for one hour, Eugene P. was called for an opportunistic access to the hall and check of the BOM
* unsuccessful attempt. Eugene P. instructed to call Ben Raydo starting next week in any opportunistic access to the hall.
* I was requested to have a short run (~30) with empty target, so we proceed to empty it (emptied ~19:00)
* here starting the issues with the HV control, being unstable the voltage difference bias between the layers
* I access the hall to connect the shunt to GEM3 Out HV
* changed set values to the HV (voltages and current for different layers)
* Empty target run finished ~21:00. Beam stopped to fill the target.
* most of the time was trying to solve the HV isssues.
* Mohammad took control remotely of the HV problem
* mainly was a sudden ramping down of the cathode without apparent reason
* the solution (I guess temporal), is to off-on in expert mode the channel ramping down to make it start ramping up to the set voltage.
* it was set an alarm everytime the RTPC HV starts to ramp down so the shift taker can execute the solution inmediately.
* First production run (240nA @ D2) started at 10:50, finished at 11:55
The only apparent issues to solve:
* BOM (under control)
* RTPC HV (more critical)
I think that we are not bad in the schedule although the problems we got.
Logbook Shift summaries:
Day: https://logbooks.jlab.org/entry/3806513
Swing: https://logbooks.jlab.org/entry/3806686
We will have the Daily Run Group F Coordination Meeting at 10AM via BlueJeans
https://bluejeans.com/7576835804
Cheers
-Carlos
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bonuslist/attachments/20200321/23af9a88/attachment.html>
More information about the Bonuslist
mailing list