[Bteam] meeting results
Jay Benesch
benesch at jlab.org
Wed Sep 15 15:11:10 EDT 2010
The group made a tentative schedule for the next nine days. All of the
info is on the whiteboard. If you can't read it, ask me for an
interpretation.
http://opsntsrv.acc.jlab.org/ops/MCC_whiteboard/MCC_scheduling_whiteboard.html
gets you to the first week.
The pathlength vs temperature test is to begin a week from today just
after the 8am meeting. See whiteboard #2. Inlet LCW temperature, i.e.
the regulation temperature, is to be increased from 95F to 110F. Outlet
temperature should be ~122F at 5.6 GeV per Mark Wiseman. Hoses are
rated at 140F, or rather were at installation.
Physics is to begin in halls A and B Monday September 27 if the ESR is
fixed by Monday Sept. 20. In hall B alone if it's not fixed until
later. Hall C will be delayed to Oct. 4 or so.
Jay