[Bteam] BTeam Agenda: Tue 7 Feb 2012

Todd Satogata satogata at jlab.org
Tue Feb 7 09:49:15 EST 2012


BTeamers,

Here is the agenda for today's BTeam meeting, at 11:00 in the MCC meeting
room as usual. We have a full plate this week with m56 setup, C100 testing
(including operational considerations) and continued anticipation of the
5-pass spin-up later in the month. Thanks to Alex Bogacz for running a good
meeting last week -- we'll see you there this week. Cheers!

-Todd


  BTeam-2012-02-07


    1 Optics on Call Report/Schedule

  * 31 Jan-07 Feb: Yuhong/Geoff
      o SL has still been running few degrees off crest to reduce Compton backgrounds
      o m56 ATLis developed, in place for Weds Feb 8 beam studies
  * 07 Feb-14 Feb: Balsa/Todd
      o TODO m56 Weds Feb 8 beam studies
      o TODO Readdress injection matching to NL, SL gang phase, Hall C Compton
      o TODO Restore SL MOMOD after SL on crest, confirm good Hall C Compton rates (Tief/ops)
      o TODO Diagnose intermittent problems in NL MOMOD (Musson? Tief? Plawski?)
  * 14 Feb-21 Feb: Fanglei/Mike Spata
      o TODO 5-pass spin-up schedule? Mid-February for Hall A, but early Feb for Hall B shift?
  * 21 Feb-28 Feb: Todd/Jay
  * 28 Feb-06 Mar: Rui/Tief
  * 06 Mar-13 Mar: Vasily/Yves
  * 13 Mar-20 Mar: Balsa/Alex
  * 20 Mar-27 Mar: Yuhong/Geoff
  * 27 Mar-03 Apr: Ed/Todd
  * 03 Apr-10 Apr: Fanglei/Mike


    2 C100 Status

  * Have been running well with 2L24 since Thu 26 Jan with few problems
  * Zone ESET is 75.04 MeV (GSET 13.4 for each cavity)
  * Possible interest in running 2L25 or both 2L24/25, increasing gradient?


    3 Manual linac RF cresting

  * QWeak cannot run while Krest is running
  * We should routinely manually touch up cresting
  * ~15 minutes by two experienced operators


    4 Beam Studies Report 1 Feb 2012 (Wednesday)

  * Studies scheduled 08:00-20:00
      o *[X]* ------ 1.0 Optics: Fopts/allsaves (good fopt/pathlength e1662787 <https://cebaf.jlab.org/elog/entry/1662787> by Alex)
      o [-] a11932 <https://cebaf.jlab.org/atlis/task/11932> 8.0 C100: Radiation Production Characterization of C100-1/2 (Drury) e1663152 <https://cebaf.jlab.org/elog/entry/1663152>, mostly completed 2L24, some cleaned up field emission
      o *[X]* a11952 <https://cebaf.jlab.org/atlis/task/11952> 2.0 PEPPo: Measure low current limit of BCM0L02 Receiver (Grames)
      o *[X]* a11690 <https://cebaf.jlab.org/atlis/task/11690> 6.0 Mott: DAQ @31 MHz with TOF bg veto (Suleiman/Grames) e1663094 <https://cebaf.jlab.org/elog/entry/1663094>, very sucessful!
      o [o] a11933 <https://cebaf.jlab.org/atlis/task/11933> --- Program: Hall C Compton bg vs laser pulse width (Tiefenback) e1663154 <https://cebaf.jlab.org/elog/entry/1663154>, injector preliminaries were set up per info in ATLis
      o [-] a11550 <https://cebaf.jlab.org/atlis/task/11550> --- Model: ZigZag Harp Development at IHA0L07 (Tiefenback/Bodenstein)
      o *[X]* ------ 2.0 Optics: Restoration
  * TODO Optics should write notes, observations of fopt/etc to Bteam elog
  * TODO Update/close out ATLis items after beam studies time, further analysis


    5 Beam Studies Scheduled 8 Feb 2012 (Wednesday)

  * TODO Submit ATLis items for desired beam studies for next week (15 Feb)
      o *[X]* ------ 0.5 Optics: Fopts/allsaves (fopt/pathlength)
      o *[X]* a11932 <https://cebaf.jlab.org/atlis/task/11932> 2.0 C100: Radiation Production Characterization of C100-1/2 (Drury, PARASITIC)
      o *[X]* a11955 <https://cebaf.jlab.org/atlis/task/11955> 8.0 Program: Injector m56 Setup (Krafft/Roblin/Benesch/Satogata/etc)
      o *[X]* a11979 <https://cebaf.jlab.org/atlis/task/11979> 1.0 PEPPo: Magnet Test (Grames)
      o *[X]* ------ 2.0 Optics: Restoration


    6 Next week

  * Hall B going to 5th pass around Feb. 15 (Hall C 3rd pass)

    ======================================================================


    7 Measuring Bunch Length using 1A Sync Light Monitor (Tief)

  * New BTeam elog entry on this procedure: e1661304 <https://cebaf.jlab.org/elog/entry/1661304>
  * TODO Prioritize and projectize for long down (12 GeV cameras, Arne)


    8 Improvements to Krest vs manual cresting, impact in 12 GeV era


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20120207/d4942c18/attachment-0002.html>


More information about the BTeam mailing list