Here it is....a chronological beam study list for 5/4-18, as we discussed it this afternoon:

    - SR compensation coils, hardware check & calibration (4h) 	(Tief)		5/4

    - Cross-talk test (4h) 					(Jay)		5/4

    - Large Dynamic Aperture Diagnostic Stations work 		(Joe Gubeli, Kevin Jordan)
	 Part I -tunnel access (4h)						5/4
	 Part I/I/  - instrumentation work (4h)					5/7
	 Part I/II/  - instrumentation work (4h)					5/13

    - autoquad commissioning with beam (4) 			(Michele)	5/5
    - phaser commissioning with beam (4h) 			(C. Slominski)	5/5
    - ITV system commissioning with beam (4h) 			(J. Krotze)	5/5

    - Energy/cavity calibrations					(Jay)		
	Part I	(10h)								5/6
	Part II	(10h)								5/14

    - Injector beam co-linearity test (6h) 			(Alicia et al)	5/8
    - Injector procedure check (4h)	 			(Alicia)	5/8

    - Spr/Rec tuning procedure improvements (4h)			(Yves)		5/8

    - RTI test (6h)						(Mahmoud)	5/11		

    - Dogleg focusing study (6h)					(Tief)		5/12

I hope I caught it all. Thanks.

		Alex


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20150428/3637c1b2/attachment-0002.html>


More information about the BTeam mailing list