[BTeam] tentative test plan and reconfiguration schedule through year-end

Jay Benesch benesch at jlab.org
Tue Nov 21 16:07:39 EST 2023


as discussed at the B team meeting this afternoon and in subsequent email exchange

11/28 HALLA FFB testing/restoration (4 hours)  BSLIST 110062 
12/1 ~0830  bleed-through script  https://tasklists.jlab.org/bslist/tasks/110314 (30 minutes)
12/1 ~0900 Wien angle change to -50 degrees, move Hall A to second pass
                 ends ~1430, six hours total on day shift
12/4  0700 Hall A turns off until late March 2024  RadCon survey for restricted access. 
12/5 Wien test plans relevant to parity BSLIST 109792,109230, 109791  0830-1630?
12/12 ~0815 SEE BPM With Stripline Can Response Test https://tasklists.jlab.org/bslist/tasks/110341 (1 hr), CW to Hall C 
12/12 ~0915 wien filter coupling study (4 hours)  BSLIST 110163 
12/20 0700 beam off for winter break 


More information about the BTeam mailing list