Good Morning Marco:

Patrizia will be meeting with the Amrit's group at 1:30 today to
discuss RICH and this issue in particular. We should have more
information by this afternoon.

Walt

Marco Battaglieri wrote:
> Dear Amrit and Amanda,
> we watched Walt's video and as far as we understood, the FT area is 
> not affected by the current plan. Are you sure that using the back 
> door will be possible? it would mean to keep free  the present FT area 
> and all the space in front of it (where RICH cabinets would be 
> located, according to the video).
> According to the existing schedule we are moving the FT to the Hall in 
> November. If it is confirmed we will free the area well in time for 
> the beginning of RICH assembly. If the FT move will be delayed, we can 
> think of moving the FT and related equipment to the right side of the 
> room in October-November when we will have people onsite from FT team 
> (Genova, Saclay Edinburgh) since the move implies recabling 
> everything. By the way, this would also imply to (re)move all the 
> cabinets, dark box and other equpment currently present on the right 
> side of the room that does not belong to us (Stepan?)
> Let us know waht you think.
> Cheers
> Marco and Raffaella
>
>
>
> Amrit Yegneswaran wrote:
>> since we do not know when the FT will be moved to the hall, keeping 
>> the FT in the corner would, i guess, provides in addition to the 
>> access to the rear door,  a secluded area where one can test the 
>> system undisturbed, till it is moved to the hall.
>>
>>
>> On 8/8/2016 11:17 AM, Amanda Hoebel wrote:
>>> Dear Marco,
>>>
>>> We have seen a video that Walt Akers made regarding the arrangement 
>>> of EEL-125 for the SVT, MicroMegas, and RICH access to the EEL-124 
>>> clean room. The video can be found via this link: 
>>> https://www.youtube.com/watch?v=W9-A36wYoIE
>>>
>>> If we could make the back roll-up door accessible, the RICH could be 
>>> moved and assembled independently of the SVT and MicroMegas. In 
>>> order to make the back roll-up door accessible, we were wondering if 
>>> the Forward Tagger could be moved to a different area of EEL-125, 
>>> possibly where the HPS equipment is stored. Would it be possible to 
>>> move both the HPS equipment and the Forward Tagger? Thanks in advance.
>>>
>>> Sincerely,
>>> Amanda
>>>
>>>
>>> _______________________________________________
>>> Dsg-ft mailing list
>>> Dsg-ft at jlab.org
>>> https://mailman.jlab.org/mailman/listinfo/dsg-ft
>>> _______________________________________________
>>> Dsg-internal mailing list
>>> Dsg-internal at jlab.org
>>> https://mailman.jlab.org/mailman/listinfo/dsg-internal
>>
>>
>> _______________________________________________
>> Dsg-ft mailing list
>> Dsg-ft at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/dsg-ft
>




More information about the Dsg-ft mailing list