[Dsg-hallb_magnets] Solenoid - Pre-Power up Check list completed
    Amrit Yegneswaran 
    yeg at jlab.org
       
    Mon Sep 11 11:00:47 EDT 2017
    
    
  
with regards to your interlock checkout contribution, great work pablo and brian. 
From: "Pablo Campero" <campero at jlab.org> 
To: "dsg-hallb magnets" <dsg-hallb_magnets at jlab.org> 
Sent: Monday, September 11, 2017 10:44:18 AM 
Subject: [Dsg-hallb_magnets] Solenoid - Pre-Power up Check list completed 
Hello Amrit, 
For your information, on late Friday (9/8/2017), Brian and I completed with the interlock checkouts and instrumentation checks required prior to the Solenoid power up. 
Solenoid has been powered up at 100 A during the weekend (9/10/2017). Data acquired during the rump up/down of the magnet will be analyzed this week to then proceed with the full current (2416 A) power up. 
Best Regards, 
Pablo 
_______________________________________________ 
Dsg-hallb_magnets mailing list 
Dsg-hallb_magnets at jlab.org 
https://mailman.jlab.org/mailman/listinfo/dsg-hallb_magnets 
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20170911/d1a85ba0/attachment.html>
    
    
More information about the Dsg-hallb_magnets
mailing list