[Dsg-hallb_magnets] Torus checkout complete for today

Ruben Fair rfair at jlab.org
Mon Jul 13 13:04:11 EDT 2020


Thank you so much guys - really appreciate it.

And thank you for posting the elogs - I am presently going through them.

Ruben
________________________________
From: Dsg-hallb_magnets <dsg-hallb_magnets-bounces at jlab.org> on behalf of Tyler Lemon <tlemon at jlab.org>
Sent: Monday, July 13, 2020 1:02 PM
To: dsg-hallb magnets <dsg-hallb_magnets at jlab.org>
Subject: [Dsg-hallb_magnets] Torus checkout complete for today


Hi Probir,

Pablo and I have finished the Torus checkouts for today.

We still have the hardware liquid helium level and liquid nitrogen level interlock to test. Those values stayed at 100% for the entire time we tried testing it. We’ll check this tomorrow.

We also have to measure the voltage inside the MPS, still.

Since we’ve completed all we can do today in the Hall, we are both returning home to telework the remainder of the day. As discussed, I took the voltage sources and your tool box with me so they do not get lost.

We will be back tomorrow at 8am.

Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20200713/34c98528/attachment.html>


More information about the Dsg-hallb_magnets mailing list