Tyler:
The contingency plan is to queue the incoming material until
the space becomes available. Some space has been reserved
in the adjacent EEL-125 area, and space can also be allocated
in the Experimental Staging Building. Because many activities
(from all of the Halls) are happening concurrently, I won't be
able to specify the exact location where the material will go
until closer to the decision point.
Walt
Tyler Lemon wrote:
> Dear Walt,
>
> Since the clean room layout where RICH is rotated 90 degrees would be
> best for the assembly, that should be considered the final layout for
> how EEL 124 will be set up for RICH assembly.
>
> Also, it seems that only one R3 drift chamber has been moved out of
> the clean room and put in Hall B. The RICH assembly structure and
> detector frame are expected to arrive at JLab in November. Is there a
> contingency plan for the clean room layout if R3 DCs do not leave by
> November? Could they be moved to the shower curtain room or to where
> other DC regions were previously stored?
>
> Best regards,
> Tyler
> ------------------------------------------------------------------------
> *From: *"Mirazita Marco" <Marco.Mirazita at lnf.infn.it>
> *To: *"Walt Akers / JLAB" <akers at jlab.org>
> *Cc: *"Patrizia Rossi" <rossi at jlab.org>, "clas12 rich"
> <clas12_rich at jlab.org>, "dsg-rich" <dsg-rich at jlab.org>
> *Sent: *Wednesday, October 26, 2016 4:28:24 AM
> *Subject: *Re: [Clas12_rich] EEL 124 layout for RICH assembly
>
> Dear Walt,
> thank you for the information, we will check with our space
> requirements.
> Marco
>
>
> Il 2016-10-25 19:15 Walt Akers / JLAB ha scritto:
> > Here you go Marco...
> >
> > As you can see from the sketch, the overall size of the vestibule and
> > air lock are similar to what was shown in the earlier drawings. The
> > most notable issue is the presence of the electrical breaker panel
> > and fire extinguisher at the rear of the room. The safety keep out
> > area
> > for those will have to be observed in your planning.
> >
> > Walt
> >
> > Marco Mirazita wrote:
> >> Dear Walt,
> >> the DSG informed us that, because of the current location of the SVT,
> >> the layout of the RICH assembly in the EEL-124 has been changed as in
> >> the attached file EEL124-rich_sept2016.jpeg.
> >> While it is in principle fine for us to move the RICH close to the
> >> gowning and air shower rooms, the RICH should be rotated by 90
> >> degrees, as in the file EEL124_Preliminary Layout 13-10-2106.jpg.
> >> In addition, we would check the available space around the RICH in
> >> order to be sure that the gantry crane could be operated properly.
> >> However, we don't have the dimension of the gowning and air shower
> >> rooms. Could you provide us this information?
> >> Thank you,
> >> Marco
> >>
> _______________________________________________
> Clas12_rich mailing list
> Clas12_rich at jlab.org
> https://mailman.jlab.org/mailman/listinfo/clas12_rich
More information about the Dsg-rich
mailing list