[Dsg-rich] RICH stiffening tool - Load test - final report

Marco Mirazita Marco.Mirazita at lnf.infn.it
Wed Aug 2 09:57:13 EDT 2017


Hi Doug,
thank you, we will let you know as soon as we have a delivery schedule 
from the company.
Best regards,
Marco


Il 2017-08-02 15:38 Douglas Tilles ha scritto:
> When it gets here! I will load test it.   Doug
> 
> ----- Original Message -----
> From: "Marco Mirazita" <Marco.Mirazita at lnf.infn.it>
> To: "Bob Miller" <rmiller at jlab.org>
> Cc: "dsg-rich" <dsg-rich at jlab.org>
> Sent: Wednesday, August 2, 2017 9:33:36 AM
> Subject: Re: [Dsg-rich] RICH stiffening tool - Load test - final report
> 
> Hi Bob,
> we are starting the procedures for the construction of the tools for 
> the
> load test and one thing we have to define is the delivery deadline.
> Could you tell us possible dates for the load test, compatibly with 
> your
> duties?
> Thank you,
> Marco
> 
> 
> 
> Il 2017-07-26 17:20 Robert Miller ha scritto:
>> Hi Marco,
>> 
>> I will look at this today and discuss the load test with Sandro.
>> 
>> Regards Bob
>> 
>> Sent from my iPhone
>> 
>>> On Jul 26, 2017, at 9:09 AM, Marco Mirazita
>>> <Marco.Mirazita at lnf.infn.it> wrote:
>>> 
>>> Dear Bob,
>>> in this conceptual design of the lifting tool load test that Sandro
>>> produced following your suggestions, we should purchase some
>>> connection bracket in order to attach the trolley to the lifting 
>>> tool.
>>> Thus, we would be really grateful if you could send to us have your
>>> comments as soon as possible, in order to proceed with the necessary
>>> purchases.
>>> Best regards,
>>> Marco
>>> 
>>> 
>>> Il 2017-07-24 22:31 Tomassini Sandro ha scritto:
>>>> Dear Bob,
>>>> attached this email you can find the final report of the stiffening
>>>> tool FEA, Bolted connection calculations and Weld Calculations.
>>>> The report is quite long but you can focus only on the last section
>>>> from page 22 (Load test)
>>>> I will focus from now on to prepare the 2D drawings for the part
>>>> production.
>>>> Let me know please if you have any concern or you are happy with the
>>>> design.
>>>> If needed we can meet somewhere to discuss about.
>>>> Many thanks
>>>> Sandro
>>>> --
>>>> -----------------------------------------
>>>> Dr. Eng. Sandro Tomassini
>>>> Istituto Nazionale di Fisica Nucleare
>>>> Laboratori Nazionali di Frascati
>>>> ---Research Division---
>>>> P.O.Box 13 00044 Frascati (RM) Italy
>>>> Tel. office: +39 06 9403 2919/8089
>>>> Fax: +39 06 94032256
>>>> e-mail: sandro.tomassini at lnf.infn.it
>>>> https://urldefense.proofpoint.com/v2/url?u=http-3A__www.lnf.infn.it_&d=DwICbA&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=9YtCiIg5kE6YCo5iFAyFiMgzNCONVcBowotEOgGZ4Co&m=5iSE-Y3wVjD1NVL_RPu7cvGYd66uPsiSK0hwm5cNrnE&s=ANybg2lyUXfPP1N7X3WihgKw3Q5ZkfFhJYVFWNOPZro&e=
>>>> -----------------------------------------
>>>> _______________________________________________
>>>> Dsg-rich mailing list
>>>> Dsg-rich at jlab.org
>>>> https://mailman.jlab.org/mailman/listinfo/dsg-rich
> _______________________________________________
> Dsg-rich mailing list
> Dsg-rich at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-rich



More information about the Dsg-rich mailing list