[Dsg-rich] Upcoming RICH assembly tasks
Patrizia Rossi
rossi at jlab.org
Fri Feb 17 12:17:22 EST 2017
Marc, Brian,
thank you for the clarification. In this case, I completely agree that 9 days should be more than enough, especially now that you have already started to assembly the structure
Have a nice week-end!
patrizia
---------------------------------------------------
# Patrizia Rossi
# Jefferson Lab
# 12000 Jefferson Avenue
# Suite 5
# Newport News VA 23606 (USA)
# e-mail: rossi at jlab.org
# phone: +1 (757) 269 7740
# fax: + 1 (757) 269 5800
# cell: +1 (757) 528 7606
> On 17/feb/2017, at 12:14, Marc McMullen <mcmullen at jlab.org> wrote:
>
> Hi Patrizia,
>
> I wrote 9 days on the BList, but this is just to complete drilling the holes and building the assembly structure. The 9 days do not account for assembly of the detector shell, that will be addressed in the TOSP.
>
> Marc McMullen
> Physics Division
> Detector Support Group
> 7738
>
> From: "rossi patrizia" <rossi at jlab.org>
> To: "Tyler Lemon" <tlemon at jlab.org>
> Cc: "dsg-rich" <dsg-rich at jlab.org>, "Rusty Sprouse" <sprouse at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "Bobby Thomas" <thomasb at jlab.org>
> Sent: Friday, February 17, 2017 11:46:18 AM
> Subject: Re: [Dsg-rich] Upcoming RICH assembly tasks
>
> Many thanks Tyler.
> Is the time estimate “9 days” the total time we anticipate to complete the work? If such I think it is underestimate
>
> patrizia
> ---------------------------------------------------
> # Patrizia Rossi
> # Jefferson Lab
> # 12000 Jefferson Avenue
> # Suite 5
> # Newport News VA 23606 (USA)
> # e-mail: rossi at jlab.org <mailto:rossi at jlab.org>
> # phone: +1 (757) 269 7740
> # fax: + 1 (757) 269 5800
> # cell: +1 (757) 528 7606
>
>
>
>
> On 17/feb/2017, at 11:38, Tyler Lemon <tlemon at jlab.org <mailto:tlemon at jlab.org>> wrote:
>
> Hello Dr. Rossi,
>
> The BList is attached. It can also be found at the link below.
>
> http://devweb.acc.jlab.org/CSUEApps/hblist/task/1460 <http://devweb.acc.jlab.org/CSUEApps/hblist/task/1460>
>
> Best regards,
> Tyler
>
> From: "Patrizia Rossi" <rossi at jlab.org <mailto:rossi at jlab.org>>
> To: "Tyler Lemon" <tlemon at jlab.org <mailto:tlemon at jlab.org>>
> Cc: "dsg-rich" <dsg-rich at jlab.org <mailto:dsg-rich at jlab.org>>, "Bob Miller" <rmiller at jlab.org <mailto:rmiller at jlab.org>>, "Bobby Thomas" <thomasb at jlab.org <mailto:thomasb at jlab.org>>, "Rusty Sprouse" <sprouse at jlab.org <mailto:sprouse at jlab.org>>
> Sent: Friday, February 17, 2017 11:22:14 AM
> Subject: Re: Upcoming RICH assembly tasks
>
> Thank you very much Tyler.
> This is indeed what I was discussing about with Marco Mirazita few days ago and asked Ed Folts to inquire.
> I understood that the B-list has been approved. May I have a copy?
>
> thanks
> patrizia
> ---------------------------------------------------
> # Patrizia Rossi
> # Jefferson Lab
> # 12000 Jefferson Avenue
> # Suite 5
> # Newport News VA 23606 (USA)
> # e-mail: rossi at jlab.org <mailto:rossi at jlab.org>
> # phone: +1 (757) 269 7740
> # fax: + 1 (757) 269 5800
> # cell: +1 (757) 528 7606
>
>
>
>
> On 17/feb/2017, at 11:20, Tyler Lemon <tlemon at jlab.org <mailto:tlemon at jlab.org>> wrote:
>
> Hello,
>
> PDF attached details the schedule and additional requirements for upcoming RICH assembly tasks through the end of March 2017.
>
> Best regards,
> Tyler
>
> <RICH assembly tasks 2017-02-17.pdf>
>
>
> <RICH assembly BList.pdf>
>
>
> _______________________________________________
> Dsg-rich mailing list
> Dsg-rich at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-rich
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20170217/7e0f5664/attachment-0002.html>
More information about the Dsg-rich
mailing list