[Dsg-rich] JLab compressor factory start-up

Frank Fair frank.fair at us.atlascopco.com
Fri Jul 14 09:17:46 EDT 2017


Tyler,

Has our service scheduler been in contact with you.

Sent from my iPad

On Jul 14, 2017, at 8:01 AM, Tyler Lemon <tlemon at jlab.org<mailto:tlemon at jlab.org>> wrote:

Hello Frank,

Both units would be ready for the factory start-up. The two units are in different locations, but will both be connected to power.

To do the start-up for both compressors, the appointment needs to be pushed back because one compressor will not be ready until the end of next week. Could we push the start-up appointment back to the week of July 24, 2017?

Best regards,
Tyler

________________________________
From: "Frank Fair" <frank.fair at us.atlascopco.com<mailto:frank.fair at us.atlascopco.com>>
To: "Tyler Lemon" <tlemon at jlab.org<mailto:tlemon at jlab.org>>
Sent: Tuesday, July 11, 2017 11:01:38 AM
Subject: RE: JLab compressor factory start-up

Tyler,

I passed the information provided to our service schedule.

Typically we require that all connections be made prior to allotting a time, and I can only provide (1) courtesy start up visit. Would it be possible to have both units ready?


Best regards,

Frank Fair
Sales Manager
Industrial Air Division
________________________________

Atlas Copco Compressors LLC

Address:

Richmond, VA 23236

Phone:

804-837-7425

E-mail:

frank.fair at us.atlascopco.com<mailto:frank.fair at us.atlascopco.com>

Visit us at:
Follow us at:

https://urldefense.proofpoint.com/v2/url?u=http-3A__www.atlascopco.us&d=DwIGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=9YtCiIg5kE6YCo5iFAyFiMgzNCONVcBowotEOgGZ4Co&m=s0XE0RtS2lrtw7BcRkCzHN_bBTCfs2qONZzo4mOe9EY&s=81odbfAHpJ4G6KcB9rwfHlXaO0-A-AgKhtqzV1_nmvQ&e= <https://urldefense.proofpoint.com/v2/url?u=http-3A__www.atlascopco.us&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=-cdWrTIbnbX9585iPzu0Zwu02sJdaQOXn_xIaWq_2dk&s=dyZY7KBp8H11MyGpayF1nW2cyITXxjAo_rChfm8qPJQ&e=>
Facebook <https://urldefense.proofpoint.com/v2/url?u=https-3A__www.facebook.com_atlascopco&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=-cdWrTIbnbX9585iPzu0Zwu02sJdaQOXn_xIaWq_2dk&s=v0YNJgIaoSaNDKGfXMqn04TP3MYMp_qbyynvlq3bPzw&e=> / Twitter <https://urldefense.proofpoint.com/v2/url?u=https-3A__twitter.com_AtlasCopcoGroup&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=-cdWrTIbnbX9585iPzu0Zwu02sJdaQOXn_xIaWq_2dk&s=OAI_zyylMNxXvd7OTX55sJqG-qawAtwLhpurgpxgNxc&e=> / LinkedIn <https://urldefense.proofpoint.com/v2/url?u=http-3A__www.linkedin.com_company_atlas-2Dcopco&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=-cdWrTIbnbX9585iPzu0Zwu02sJdaQOXn_xIaWq_2dk&s=SzbzU5J6hAh-i1d95h8LGUBZVkIF7Wnw8bc-4l6AW84&e=> / YouTube<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.youtube.com_user_atlascopcogroup&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=-cdWrTIbnbX9585iPzu0Zwu02sJdaQOXn_xIaWq_2dk&s=ID1YL8yISva0pmakjYtoekydhZvSNuEEZDWFreFFxL0&e=>

Committed to sustainable productivity


From: Tyler Lemon [mailto:tlemon at jlab.org]
Sent: Tuesday, July 11, 2017 10:36 AM
To: Frank Fair <frank.fair at us.atlascopco.com<mailto:frank.fair at us.atlascopco.com>>; dsg-rich <dsg-rich at jlab.org<mailto:dsg-rich at jlab.org>>; Donna Galpin <donna.galpin at us.atlascopco.com<mailto:donna.galpin at us.atlascopco.com>>
Subject: JLab compressor factory start-up

Hello Frank,

The serial numbers and information for the compressors we have are below. We will need the factory start-up for Compressor #1.

We have the wires to power the compressor attached, but the power supply we will be using to power the compressor still needs its ground wire attached to ground. This will be done by the time an Atlas Copco representative will be at JLab.

Could give us an estimated time and date for the service appointment?

Compressor #

Item

Serial Number

No.

Compressor Info

1

8153602704

API771370

662151

SF 11+ 100 FF LC 200

2

815362704

API773171

662151

SF 11+ 100 FF LC 200


Best regards,
Tyler

________________________________
From: "Frank Fair" <frank.fair at us.atlascopco.com<mailto:frank.fair at us.atlascopco.com>>
To: "Tyler Lemon" <tlemon at jlab.org<mailto:tlemon at jlab.org>>
Cc: "dsg-rich" <dsg-rich at jlab.org<mailto:dsg-rich at jlab.org>>, "Donna Galpin" <donna.galpin at us.atlascopco.com<mailto:donna.galpin at us.atlascopco.com>>
Sent: Tuesday, July 11, 2017 8:10:20 AM
Subject: RE: Question regarding power needed for SF 11+ 100 FF LC 200 compressors

Tyler,

I have sent an email to our service scheduler.

Can you forward the Serial Number of each compressor?

Also, please confirm that the wires are landed to the compressors.


Best regards,

Frank Fair
Sales Manager
Industrial Air Division
________________________________

Atlas Copco Compressors LLC

Address:

Richmond, VA 23236

Phone:

804-837-7425

E-mail:

frank.fair at us.atlascopco.com<mailto:frank.fair at us.atlascopco.com>

Visit us at:
Follow us at:

https://urldefense.proofpoint.com/v2/url?u=http-3A__www.atlascopco.us&d=DwIGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=9YtCiIg5kE6YCo5iFAyFiMgzNCONVcBowotEOgGZ4Co&m=s0XE0RtS2lrtw7BcRkCzHN_bBTCfs2qONZzo4mOe9EY&s=81odbfAHpJ4G6KcB9rwfHlXaO0-A-AgKhtqzV1_nmvQ&e= <https://urldefense.proofpoint.com/v2/url?u=http-3A__www.atlascopco.us&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=_JwY-NGhZDkBbCbL5dHsbiKHfPpDf8IgE9TmEvFsls0&s=L_ekvthCh996zdcMJMZErceMrKU5fLKmWeFLwymtHNc&e=>
Facebook <https://urldefense.proofpoint.com/v2/url?u=https-3A__www.facebook.com_atlascopco&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=_JwY-NGhZDkBbCbL5dHsbiKHfPpDf8IgE9TmEvFsls0&s=57aK-bmUPd1T45RFPLgOWOyW-_KwcbKg4hM-VVnd1sI&e=> / Twitter <https://urldefense.proofpoint.com/v2/url?u=https-3A__twitter.com_AtlasCopcoGroup&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=_JwY-NGhZDkBbCbL5dHsbiKHfPpDf8IgE9TmEvFsls0&s=A-toF-I0FWL6fDLUghT2Raj9XqHwaIqD9qLZBcCkWxg&e=> / LinkedIn <https://urldefense.proofpoint.com/v2/url?u=http-3A__www.linkedin.com_company_atlas-2Dcopco&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=_JwY-NGhZDkBbCbL5dHsbiKHfPpDf8IgE9TmEvFsls0&s=Y-OcsKjONfxHK27OWqjT5gvtgUda3uAoBfbq24Mug9k&e=> / YouTube<https://urldefense.proofpoint.com/v2/url?u=http-3A__www.youtube.com_user_atlascopcogroup&d=DwMGaQ&c=lz9TcOasaINaaC3U7FbMev2lsutwpI4--09aP8Lu18s&r=f-t6QoIPtnKcbZffsXp7zA&m=_JwY-NGhZDkBbCbL5dHsbiKHfPpDf8IgE9TmEvFsls0&s=XjSK6ntb4Z1MYIAjLJ5rmbPZPlxvV_I8S0Doi6Qe298&e=>

Committed to sustainable productivity





-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20170714/5924fea5/attachment-0002.html>


More information about the Dsg-rich mailing list