[Dsg-rich] INFN Stiffening Tool Status
Marc McMullen
mcmullen at jlab.org
Wed Jul 26 08:34:09 EDT 2017
Ryan,
Thanks for the response. For planning purposes, can you give an estimate
for delivery?
Thanks,
Marc
On 7/26/2017 5:55 AM, Ryan Bruce wrote:
>
> Marc,
>
> We are in the middle of fixing the front end of the
> stiffening tool to make sure it lines up with the plate that was
> provided after fabrication. As soon as that is done, we will get our
> inspector over here to sign off on it and then it will go to powder
> coating.
>
> Thank You,
>
> **
>
> *Ryan L. Bruce*
>
> Project Manager
>
> */_G&R Metals_/*
>
> */a MFS, Inc. Company/*
>
> 810 Kiwanis Street
>
> Hampton, VA 23661
>
> Ph: 757.244.5693
>
> Fax: 757.245.1132
>
> */_Ryan at gandrmetals.com <mailto:Ryan at gandrmetals.com>_/*
>
> *From:*Marc McMullen [mailto:mcmullen at jlab.org]
> *Sent:* Tuesday, July 25, 2017 9:49 AM
> *To:* Ryan Bruce
> *Cc:* dsg-rich
> *Subject:* INFN Stiffening Tool Status
>
> Hi Ryan,
>
> Our collaborators from Italy asked me to contact you about the status
> of the fabrication. As I recall the welding inspection was pending
> payment, which was set up through Jlab procurement. Has it been
> scheduled/completed? If completed how soon can they expect delivery?
>
> Regards,
>
> Marc McMullen
> Physics Division
> Detector Support Group
> 7738
>
--
Marc McMullen
Detector Support Group
757-269-7738
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20170726/b81dcd41/attachment-0002.html>
More information about the Dsg-rich
mailing list