[Dsg-rich] RICH gantry lift test

Douglas Tilles tilles at jlab.org
Fri Mar 10 06:11:58 EST 2017


Has the Lift Plan been done and signed off by Civil Eng. 

----- Original Message -----
From: "Marc McMullen" <mcmullen at jlab.org>
To: "Doug Tilles" <tilles at jlab.org>, "Denny Insley" <dinsley at jlab.org>
Cc: "dsg-rich" <dsg-rich at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "Patrizia Rossi" <rossi at jlab.org>
Sent: Thursday, March 9, 2017 4:20:14 PM
Subject: RICH gantry lift test

Hi Doug and Denny,

Tomorrow morning (3/10 at 0845 in the EEL 124 clean room) INFN and the 
DSG will perform a lift (rotation) of the RICH detector shell as 
prescribed in the approved TOSP. This will be a brief operation which 
should take less than an hour, and it will be observed by Patrizia prior 
to the CLAS 12 RICH meeting. Hall B mechanical support is needed in the 
form of an addition qualified operator for the gantry 2 ton chain fall. 
If a qualified rigger can supervise non qualified chain fall operator, 
then the additional support is not needed. I am attaching the TOSP for 
review of your operator so they can sign prior to the work.

Thanks in advance for your prompt support.


-- 
Marc McMullen