[Dsg-rich] Installation of support panels in RICH detector
Marc McMullen
mcmullen at jlab.org
Mon Mar 13 08:39:51 EDT 2017
No problem
On 3/13/2017 7:46 AM, Ed Folts wrote:
> Hi Marc
>
> It would probably be wise to fill out a B list just to cover the bases.
>
> thanks
>
> Ed
>
>
> On 3/10/2017 3:36 PM, Marc McMullen wrote:
>> Hi Ed,
>>
>> The tasks covered in TOSP are essentially complete, we will perform
>> two more lifts covered withing the scope of that TOSP.
>>
>> Next week INFN and the DSG will perform the installation of the
>> support panels for the electronics (Electronics to be installed at a
>> later date, under a new TOSP). These tasks are not covered in the
>> current TOSP, it is an intermediate task between the ones covered in
>> the current and the ones which will be covered in the installation of
>> electronics, mirrors, and PMTs. The task involves using standard
>> tools to do the installation. We will use the enclosed platform
>> stairs to work on anything greater than normal standing height. There
>> will be no use of the gantry or winch to perform these tasks. So I am
>> handling this with an informal THA as per the work planning guidance,
>> I estimate the work to take much less than 2 weeks. We will still do
>> the standard pre-job briefings prior to the shift.
>>
>> Thanks,
>>
>>
>>
>
>
--
Marc McMullen
Detector Support Group
757-269-7738