Dear all,
let me only mention CMA is supposed to provide a proper
package that can be reused by ECI after coating. Is it
not the case ?
Thanks, Marco.
On Mon, 2 Oct 2017, Barbara Monti wrote:
>
> Hello Tyler,
>
>
>
> You’re welcome. Hope you had a nice weekend. My weekend was good. Please give us a
> call or let us know your phone number and a convenient time for us to call you to
> discuss packaging details?
>
>
>
> Regards,
>
>
>
> Barbara
>
>
>
> From: Tyler Lemon [mailto:tlemon at jlab.org]
> Sent: Monday, October 02, 2017 7:53 AM
> To: Barbara Monti <bmonti at evapcoat.com>
> Cc: dsg-rich <dsg-rich at jlab.org>
> Subject: Re: ECI target schedule for INFN RICH Mirrors
>
>
>
> Hello Barbara,
>
>
>
> Thank you for sharing the mirrors' target schedule.
>
>
>
> We will start arranging the first two mirrors' shipping details.
>
>
>
> Would you be able to tell us now how the first two mirrors will be packed? We would
> need this information to complete the shipping authorization process.
>
>
>
> Please let us know.
>
>
>
> Best regards,
>
> Tyler
>
>
>
>
>
>
> _____________________________________________________________________________________
>
>
> From: "Barbara Monti" <bmonti at evapcoat.com>
> To: "Tyler Lemon" <tlemon at jlab.org>
> Cc: "dsg-rich" <dsg-rich at jlab.org>
> Sent: Friday, September 29, 2017 6:01:53 PM
> Subject: ECI target schedule for INFN RICH Mirrors
>
>
>
> Dear Tyler,
>
>
>
> As promised, here is a the preliminary target schedule for mirror completion and
> availability at ECI:
>
>
>
> 2 mirrors available for JLab transit pick-up on the afternoon of Fri 10/6 or Mon
> 10/9.
>
>
>
> 4 coated mirrors available for JLab transit pick-up on the afternoon of Fri 10/20 or
> Mon 10/23.
>
>
>
> 4 coated mirrors available for JLab transit pick-up on the afternoon of Fri 10/27 or
> Mon 10/30.
>
>
>
> We will contact you again next week with an update about progress for the first 2
> mirrors.
>
>
>
> The two additional pick-up dates for 4 mirrors each may change or be combined into
> one shipment of 8 depending upon feedback from INFN about test and evaluation results
> for the first 2 mirrors delivered.
>
>
>
> With kindest regards and happy weekend wishes,
>
>
>
> Sincerely,
>
>
>
> Barbara
>
>
>
>
>
> From: Barbara Monti [mailto:bmonti at evapcoat.com]
> Sent: Tuesday, September 26, 2017 6:12 PM
> To: 'Tyler Lemon' <tlemon at jlab.org>
> Cc: 'dsg-rich' <dsg-rich at jlab.org>
> Subject: Yes - confirm six RICH mirrors received at ECI on 9/25
>
>
>
> Hello Tyler,
>
>
>
> Thank you for your inquiry. Yes: six RICH spherical mirrors were delivered to ECI
> yesterday, September 25, 2017. We have a conference call scheduled tomorrow, 9/27,
> with Marco and Marco at INFN to discuss details about how to proceed.
>
>
>
> We will contact you again after the conference call, and once all scheduling details
> are worked out, about anticipated shipment timeline. From previous discussions with
> INFN, our understanding is JLab will be handling transportation for the upcoming RICH
> mirror shipment(s) to JLab and we will do our best to give you all the details you
> need, with as much notice as possible, for efficient coordination of our mutual
> efforts.
>
>
>
> With kindest regards,
>
>
>
> Sincerely,
>
>
>
> Barbara
>
>
>
> Barbara Monti
>
> Technical Sales
>
>
>
> Evaporated Coatings, Inc.
>
> Address: 2365 Maryland Road, Willow Grove, PA 19090 USA
>
> Phone: (215) 659-3080 Extension 220; Fax: (215) 659-1275
>
> Email: bmonti at evapcoat.com
>
> Website: www.evaporatedcoatings.com
>
>
>
>
>
> From: Tyler Lemon [mailto:tlemon at jlab.org]
> Sent: Tuesday, September 26, 2017 2:18 PM
> To: Barbara Monti <bmonti at evapcoat.com>
> Cc: dsg-rich <dsg-rich at jlab.org>
> Subject: confirm six RICH mirrors received at ECI?
>
>
>
> Hello Barbara,
>
>
>
> I can see on UPS's tracking that six RICH spherical mirrors were delivered to ECI
> yesterday, September 25, 2017.
>
>
>
> Can you confirm that the mirrors have been received at ECI?
>
>
>
> Could you also give an estimate on when the mirrors would ship from ECI to JLab after
> coating?
>
>
>
> Please let us know.
>
>
>
> Best regards,
>
> Tyler Lemon
>