[Dsg-rich] Hall B - RICH Experiment - Air compressor condensate drain piping - Cost to install
Douglas Tilles
tilles at jlab.org
Tue Oct 24 16:45:54 EDT 2017
This is not up to me it is the hall leader and Rich group
Sent from my iPhone
> On Oct 24, 2017, at 10:29 AM, Ronald Bartek <bartek at jlab.org> wrote:
>
> Doug/George/Tyler
>
> I have been able to identify areas where costs can be reduced. My latest estimated installed price using a Facilities subcontractor has been reduced from the original $12,344 to to $8977. If this estimate is deemed acceptable I will go the next step which is a design review by the user, Facilities, and ES&H.
>
> Please advise if I should proceed with this next step.
>
> <Thunderbird signature.jpg>
>
>
> From: "Ronald Bartek" <bartek at jlab.org>
> To: "George Jacobs" <jacobsg at jlab.org>
> Cc: "Tyler Lemon" <tlemon at jlab.org>, "Doug Tilles" <tilles at jlab.org>, "dsg-rich" <dsg-rich at jlab.org>, "Carroll Jones" <jonesc at jlab.org>
> Sent: Monday, October 23, 2017 4:58:22 PM
> Subject: Re: [Dsg-rich] Hall B - RICH Experiment - Air compressor condensate drain piping - Cost to install
>
> Attached are two (2) PDF's showing what is proposed. What are you suggesting we change?
>
> P.S. The estimated cost to do what is shown on the attached PDF's is:
>
> Materials: $1671.69(includes contractor contractor mark up of 21%)
> Labor using outside contractor: $7305.36. We may be able to reduce this by $1317.36 depending upon if we can let the contractor work continuously without interruptions.
>
> Your thoughts??
>
>
>
>
> From: "George Jacobs" <jacobsg at jlab.org>
> To: "Tyler Lemon" <tlemon at jlab.org>, "Ronald Bartek" <bartek at jlab.org>, "Doug Tilles" <tilles at jlab.org>
> Cc: "dsg-rich" <dsg-rich at jlab.org>
> Sent: Monday, October 23, 2017 2:59:37 PM
> Subject: Re: [Dsg-rich] Hall B - RICH Experiment - Air compressor condensate drain piping - Cost to install
>
> Can we just run a line to the drip tray of an air handler on the next level down? Or run a very long hose down to the floor where it can be directed into a floor drain?
>
> George
>
> On 10/23/2017 1:53 PM, Tyler Lemon wrote:
> Hello Ron and Doug,
>
> I do not know what any sort of budget would be to install the drain for the RICH air cooling compressors in Hall B.
>
> In July 2017 as discussed with Walt Akers and Carroll Jones, I submitted the work request to have some sort of drain installed in Hall B for the RICH compressors' condensate.
>
> We just need some way to direct the condensate ejected from the compressor so it doesn't drip down from the top of the forward carriage. The drain could just be a simple line running from the compressors to the drain on the floor.
>
> Best regards,
> Tyler
>
> From: "Ronald Bartek" <bartek at jlab.org>
> To: "Tyler Lemon" <tlemon at jlab.org>
> Sent: Friday, October 20, 2017 8:36:12 AM
> Subject: Hall B - RICH Experiment - Air compressor condensate drain piping - Cost to install
>
> Tyler
>
> Do you have a "budget" number for installing the condensate drain system?
>
>
>
>
>
>
> _______________________________________________
> Dsg-rich mailing list
> Dsg-rich at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-rich
>
> --
> George Jacobs
> Jefferson Lab (TJNAF)
> STE 12
> 12000 Jefferson Ave.
> Newport News, VA 23606
>
> (office) 757-269-7115
>
> (cell) 757-876-0480
>
> (email) jacobsg at jlab.org
>
> (website) https://userweb.jlab.org/~jacobsg
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20171024/a9cf8db3/attachment-0002.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Thunderbird signature.jpg
Type: image/jpeg
Size: 31486 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20171024/a9cf8db3/attachment-0002.jpg>
More information about the Dsg-rich
mailing list