[Dsg-rich] Fwd: Move RICH to the Hall on Wednesday due to Snow Forecast

Marco Contalbrigo mcontalb at fe.infn.it
Fri Jan 5 10:01:35 EST 2018


Hi Tyler and DSG,
at noon Dario and Sandro will be in EEL available for RICH
preparation. To my understanding the actions will be:

- disconnect the dewars and plug a N2 bottle
   is there a designated place ?
   can the bottle be fixed on the trolley ?

- disconnect the interlock cables

- put the patch panels in close/safe position

- wrap the RICH with a protective plastic layer

- install a temporary N2 supply line in Hall-B

- put the trolley on its wheels
   can we use the hydraulic jack even with the RICH weight ?
   are the tires all fine ?

- free space in the target area

Thanks, Marco.

On Thu, 4 Jan 2018, Tyler Lemon wrote:

> From: "Robert Miller" <rmiller at jlab.org>
> To: "Marco Contalbrigo" <mcontalb at fe.infn.it>
> Cc: "Tomassini Sandro" <sandro.tomassini at lnf.infn.it>, "Mirazita Marco"
> <Marco.Mirazita at lnf.infn.it>, "Tyler Lemon" <tlemon at jlab.org>
> Sent: Thursday, January 4, 2018 6:37:55 PM
> Subject: Re: Move RICH to the Hall on Wednesday due to Snow Forecast
> 
> Hi Marco,
> 
> Start working in the clean room at noon and move the RICH out of the clean room
> door when you are ready.  I need to go to the Hall first, then I will be in the
> clean room around 1pm.  Call me on my cell if you need anything 757 822-9586.  I
> assume that the DSG is setting up the nitrogen to go on the truck.
> 
> Regards,
> Bob
> 
> ----- Original Message -----
> From: "Marco Contalbrigo" <mcontalb at fe.infn.it>
> To: "Bob Miller" <rmiller at jlab.org>
> Cc: "Tomassini Sandro" <sandro.tomassini at lnf.infn.it>, "Marco Mirazita"
> <Marco.Mirazita at lnf.infn.it>, "Tyler Lemon" <tlemon at jlab.org>
> Sent: Thursday, January 4, 2018 6:27:46 PM
> Subject: Re: Move RICH to the Hall on Wednesday due to Snow Forecast
> 
> Hi Bob,
> thanks for the information. At which time should we meet
> in EEL building to start ?
> Regards, Marco.
> 
> On Thu, 4 Jan 2018, Robert Miller wrote:
> 
> > Hi Marco,
> >
> > The lab opens at noon on Friday, so we should move the RICH to the Hall on Friday
> afternoon and install it Saturday morning.
> >
> > Regards,
> > Bob
> >
> > ----- Original Message -----
> > From: "Marco Contalbrigo" <mcontalb at fe.infn.it>
> > To: "Bob Miller" <rmiller at jlab.org>
> > Cc: "Tomassini Sandro" <sandro.tomassini at lnf.infn.it>, "Marco Mirazita"
> <Marco.Mirazita at lnf.infn.it>, "Patrizia Rossi" <rossi at jlab.org>, "Marc McMullen"
> <mcmullen at jlab.or>, "Tyler Lemon" <tlemon at jlab.org>, "Benjamin Raydo"
> <braydo at jlab.org>, "C. Cuevas" <cuevas at jlab.org>
> > Sent: Wednesday, January 3, 2018 3:51:08 PM
> > Subject: Re: Move RICH to the Hall on Wednesday due to Snow Forecast
> >
> > Pretty nice. Thank you all!
> > Just a potential issue: one of the trolley tires was loose
> > before Christmas. This is something may need to be taken
> > care of, if not already done.
> > Thanks, Marco.
> >
> > On Wed, 3 Jan 2018, Robert Miller wrote:
> >
> >> Hi Marco,
> >>
> >> Everything is ready for transporting and installing the RICH:
> >>
> >> The truck is in the EEL building. The cables have been disconnected by Chris
> Cuevas and he will install the crates and cables in the hall.  The installation
> tooling is set up in the Hall, and the forward carriage is in the maintenance
> position.
> >>
> >> I will contact you when we return from the snow delay.
> >>
> >> Regards,
> >> Bob
> >>
> >> ----- Original Message -----
> >> From: "Marco Contalbrigo" <mcontalb at fe.infn.it>
> >> To: "Bob Miller" <rmiller at jlab.org>
> >> Cc: "Tomassini Sandro" <sandro.tomassini at lnf.infn.it>, "Marco Mirazita"
> <Marco.Mirazita at lnf.infn.it>, "Patrizia Rossi" <rossi at jlab.org>, "Marc McMullen"
> <mcmullen at jlab.or>, "Tyler Lemon" <tlemon at jlab.org>, "Benjamin Raydo"
> <braydo at jlab.org>
> >> Sent: Tuesday, January 2, 2018 10:42:47 AM
> >> Subject: Re: Move RICH to the Hall on Wednesday due to Snow Forecast
> >>
> >> Hi Bob,
> >> fine with us. As soon as at JLab, we will do our best to get the RICH
> >> ready to go at the earliest weather copnvenience. The effort to
> >> uncable the RICH and prepare the crates (except interlock that will
> >> move together with RICH) is in the hand of Electronics Group:
> >> Ben is in cc.
> >> Thanks, Marco.
> >>
> >> On Tue, 2 Jan 2018, Bob Miller wrote:
> >>
> >>> Hi Marco,
> >>>
> >>> The Hall B installation schedule only has one day of contingency before we
> >>> run beam, therefore we will install the RICH as soon as possible.
> >>>
> >>> Hall B is prepared to transport and install the RICH.
> >>>
> >>> When you arrive, please prepare the RICH as soon as you can, then we will
> >>> transport it as soon as the weather permits.  I would like to install the
> >>> detector on Friday as planned, but it may have to be Saturday.
> >>>
> >>> What can be done in the clean room before you arrive to prepare the RICH for
> >>> transport?
> >>>
> >>> Hi Tyler,
> >>>
> >>> The crates and cables are scheduled to be moved to the Hall on Wednesday and
> >>> installed on the forward carriage.  Who is leading that effort and who will
> >>> run the cables on the forward carriage? Are the cables and crates ready to be
> >>> moved?
> >>>
> >>> Regards,
> >>>
> >>> Bob
> >>>
> >>>
> >>> On 1/2/2018 9:02 AM, Marco Contalbrigo wrote:
> >>>>  Dear Bob,
> >>>>  moving the RICH without Dario and Sandro, who knows details and
> >>>>  criticalities, is a risk we should not take. Wednesday is by
> >>>>  far the worse day as they (and me) will be unreachable because
> >>>>  travelling to Jlab.
> >>>>
> >>>>  Weather forecast is not fully reliable, some predicts snow
> >>>>  already on Wednesday. If the snow is a issue for JLab opening,
> >>>>  we should avoid to rush moving the RICH and be stuck before
> >>>>  having it in the final safe position.
> >>>>
> >>>>  My porposal is:
> >>>>  Thursday 4th: prepare RICH on truck
> >>>>  Friday 5th: move RICH into the Hall
> >>>>  Monday 8th: install RICH on forward carriage
> >>>>  Tuesday 9th: survey the RICH
> >>>>
> >>>>  According to your schedule, this has no ipact on Hall-B
> >>>>  preparation for beam. The drawback is to have the RICH
> >>>>  in a park position for the week-end. Having time to
> >>>>  prepare the gas line in advance in the Hall, I do not see
> >>>>  a real problem.
> >>>>
> >>>>  If preferable for Hall-B scheduling, we can install the
> >>>>  RICH on the forward carriage Saturday the 6th.
> >>>>
> >>>>  Best regards, Marco.
> >>>>
> >>>>  On Tue, 2 Jan 2018, Bob Miller wrote:
> >>>>
> >>>>>  Hi Marco,
> >>>>>
> >>>>>  We have a forecast for snow on Wednesday afternoon and evening.
> >>>>>  Therefore, we need to move the RICH to the Hall Wednesday morning instead
> >>>>>  of Thursday.  The Hall and truck will be ready, let me know if the RICH
> >>>>>  will be ready to move out of the clean room at 9am Wednesday morning.
> >>>>>
> >>>>>  Thanks,
> >>>>>
> >>>>>
> >>>
> >>>
> >>
> >
> 
>