[dsg-hallb_rich] [EXTERNAL] Re: RICH-II space requirements

Tyler Lemon tlemon at jlab.org
Mon Jan 11 11:58:43 EST 2021


Hello Marco,

Thank you for your reply.

I submitted the procurement request for the new dry box this morning.

I expect that the JLab procurement process will take two to three weeks and then an additional three to four weeks for the dry box to be delivered.

-Tyler
________________________________
From: Marco Mirazita <Marco.Mirazita at lnf.infn.it>
Sent: Monday, January 11, 2021 10:12 AM
To: Patrizia Rossi <rossi at jlab.org>
Cc: Tyler Lemon <tlemon at jlab.org>; dsg-hallb_rich at jlab.org <dsg-hallb_rich at jlab.org>
Subject: [EXTERNAL] Re: [dsg-hallb_rich] RICH-II space requirements

Hello Tyler,
thank you for this work. I don't have much to add on your space
requirement estimate.
Here few updates on the shipments:

1) The RICH shell is ready to be shipped, it should depart in a couple
of weeks and it will take about 40 days to arrive at JLab.
It will be made by two big boxes containing all the elements of the RICH
shell, including the electronic panel and the frontal panels.
I'm waiting to have from the company the size and the weight of the two
boxes.
As soon as all the documents are ready, I will start the procedure by
contacting all the people involved.

2) The planar mirrors have not been shipped yet because the company has
to redo one of them. I don't have any defined delivery schedule yet, but
I would say it will take at least one month from now.

3) The aerogel is almost ready, but we will wait to have installed the
new dry cabinet. Do you know when this may happen?

4) The spherical mirror support will come late during this year. The
construction has not been awarded yet.

Best regards,
Marco




Il 2021-01-11 15:40 Patrizia Rossi ha scritto:
> Hi Tyler and DSG,
>
> Thanks for working to assess the space requirements for the assembly
> and testing of the second RICH module.
>
> I agree on your conclusions but I would like Marco M. and Marco C. to
> confirm.
>
> Have a nice day
>
> patrizia
>
> FROM: dsg-hallb_rich <dsg-hallb_rich-bounces at jlab.org> on behalf of
> Tyler Lemon <tlemon at jlab.org>
>  DATE: Sunday, January 10, 2021 at 10:24 AM
>  TO: "dsg-hallb_rich at jlab.org" <dsg-hallb_rich at jlab.org>
>  SUBJECT: [dsg-hallb_rich] RICH-II space requirements
>
> Hello Patrizia, Marco Mirazita, and Marco Contalbrigo,
>
> We received an email from Walt Akers asking about any space needs for
> upcoming projects.
>
> We discussed the space requirements for the assembly and testing of
> the second RICH module in Friday's DSG RICH R&D meeting. Attached are
> a few slides detailing the outcome of the discussion.
>
> In short we will be requesting from Walt the same amount of space that
> was used for the assembly of RICH-I.
>
> If there are no questions or additions to the slides, we will forward
> them to Walt this coming week.
>
> -Tyler
> _______________________________________________
> dsg-hallb_rich mailing list
> dsg-hallb_rich at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-hallb_rich

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20210111/b305b0c4/attachment.html>


More information about the dsg-hallb_rich mailing list