Hi all,
today the RICH has been transported in Hall B and has been attached to
the LTCC strong back. The installation in CLAS will be completed
tomorrow morning.
The cabling has been also started.
The detector was temporarily connected to the hall nitrogen supply to
keep the aerogel safe. Two sensors close to the aerogel were also
connected. The internal humidity is smoothly going down from the initial
6% level.
Marco
-------------- next part --------------
A non-text attachment was scrubbed...
Name: IMG_20220601_151458_resized_20220601_083416613.jpg
Type: image/jpeg
Size: 2621070 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20220602/13f47066/attachment-0001.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RichHumidity.png
Type: image/png
Size: 116735 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20220602/13f47066/attachment-0001.png>
More information about the dsg-hallb_rich
mailing list