Dear All,
BMT integration and cabling is complete. All tiles are operational,
tested with premix gas under the nominal HV settings. Pedestals are
posted to the HBMVT elog. BMT is being flushed with argon. Bob will
mount the BMT on the integration cart on Friday.
SVT cabling is complete. All modules are operational, calibration
results are posted to the HBSVT elog. SVT sensors will be kept cold
until the survey.
Per agreement with Chris next week the survey group will do SVT survey
and BMT alignment (after it is integrated with the SVT on the cart).
After the integration the CVT will be transported to the hall, craned to
the space frame, and mounted on the CVT cart. At this stage we would
need support from the Detector Support Group to rout and connect the
cables to the crates. We also rely on help from Mohammad in June to
commission the tracker and from the Fast Electronics group on
reinstalling the cosmic trigger to collect alignment data during the
summer time. If travel restrictions will be eased, CEA team will join us
on the work in the hall.
Yuri and Rafayel
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20210512/fa85808c/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: gotra.vcf
Type: text/x-vcard
Size: 102 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20210512/fa85808c/attachment.vcf>
More information about the dsg-hallb_svt
mailing list