[Esr-users] Hall C Testing
Jessie Butler
jbutler at jlab.org
Tue Aug 7 07:43:10 EDT 2018
Hi Steve,
We are currently in the process of cooling down our magnets in Hall A so we are flowing back on warm return. Dumps in Hall C (or Hall B) will affect our progress and likely create issues within our cryogenic and vacuum systems. Is it possible for you to postpone these tests until Hall A is cold and on cold return? At the current rate, Hall A should be on cold return and stable NLT Aug 17th.
Thanks,
Jessie Butler
Jefferson Lab
Physics/Hall-A Work Coordinator
757-269-5544
EXCELLENCE IS OUR STANDARD;
PERFECTION IS OUR GOAL.
More information about the Esr-users
mailing list