Robert Michaels
rom at jlab.org
Fri Mar 12 08:42:52 EST 2010
That's great news about the Compton from Sirish.
It was the last remaining "big" uncertainty
for starting PREX.
Now we have a complex commissioning program ahead
of us, which is mostly expert-driven
https://prex.jlab.org/wiki/index.php/RunPlan
The daily run plan will be updated by the RC
https://prex.jlab.org/wiki/index.php/RunPlanDaily
We start daily meetings on Tuesday March 16.
Each day we meet at 3 pm in the 2nd floor CH.
Yesterday we had a PREX meeting with updates
on subsystem progress (URL below). Detector
installations will continue through the weekend.
There's still some work to do on Compton.
Work in the target area is projected to be
finished by approx. 5 pm Tuesday, so shifts
may start next Wednesday Mar 17 (day shift).
Meeting minutes, March 11
http://hallaweb.jlab.org/parity/prex/mtg/mtg_11mar10.html
Index of meeting minutes
http://hallaweb.jlab.org/parity/prex/mtg
The next RC is Richard Holmes; he starts Monday.
Bob Michaels
present Run Coordinator
On Fri, 12 Mar 2010, nanda at jlab.org wrote:
> Dear All,
>
> We got the new green Compton cavity in Hall A to lock to the fiber
> amplified PPLN green laser successfully!
>
> Although careful calibration of detectors are yet to be done, my rough
> estimate is that it locked at around 60-70% of design power. Optics tweaks
> and electronics tricks should bring the cavity to peak power in the coming
> days.
>
> With this major milestone achieved, the Compton Upgrade project is now
> ready in full scope - green cavity, GSO photon detector, and microstrip
> electron detector - for commissioning with beam for PRex.
>
> Sirish
>
> _______________________________________________
> Halla_parity mailing list
> Halla_parity at jlab.org
> https://mailman.jlab.org/mailman/listinfo/halla_parity
>