[Halla_running] Counting house computers will be down
Ole Hansen
ole at jlab.org
Wed Sep 10 14:09:52 EDT 2014
On 09/10/2014 01:59 PM, Walt Akers / JLAB wrote:
>
> Keep in mind, because of the diversity of power sources that service the
> Counting House and the Halls, I can not guarantee that this generator will
> support everything - JUST the receptacles that are labeled emergency
> power.
>
That would be enough to keep the DAQ computers and network switch in the
counting house running for DVCS.
I don't know what power feed is used for adaqfs on the second floor of
the counting house. That machine did go down along with all others
plugged into "emergency power" recently, so it looks like it is on that
line, which is good (assuming generator power materializes). adaqfs is
required for DAQ operations (home directories, name server etc). In the
worst case (no emergency power available upstairs), we could move that
machine to the computer room downstairs and run it off the emergency
power - it's an easy job.
Ole
-------------- next part --------------
A non-text attachment was scrubbed...
Name: ole.vcf
Type: text/x-vcard
Size: 333 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/halla_running/attachments/20140910/0d813a8c/attachment.vcf
More information about the Halla_running
mailing list