[Hallb-engineering] Fwd: Lesson Learned "Technician Receives Mild Shock while Troubleshooting a Portable Air Sampler - : Nuclear Waste Partnership, LLC"
Douglas Tilles
tilles at jlab.org
Wed Jul 15 08:08:23 EDT 2015
FYI
----- Forwarded Message -----
From: "mbailey" <mbailey at jlab.org>
To: "mbailey" <mbailey at jlab.org>
Sent: Tuesday, July 14, 2015 4:00:09 PM
Subject: Lesson Learned "Technician Receives Mild Shock while Troubleshooting a Portable Air Sampler - : Nuclear Waste Partnership, LLC"
Jefferson Lab Lessons Learned : Print Lesson
Technician Receives Mild Shock while Troubleshooting a Portable Air Sampler - : Nuclear Waste Partnership, LLC
Statement of Lessons Learned
For a copy of the original report, see �Attachments� on Lessons Learned page.
A Radiological Control Technician (RCT) attempted to fix a faulty portable air sampler by removing its fuse and replacing it. When the sampler continued to fail the RCT attempted to remove the second fuse, but did not disconnect the sampler from the electrical supply, and experienced a mild tingling sensation.
Discussion of Activities
On March 4, 2015 a RCT attempted to start a portable air sampler, but the instrument would not turn on. Based on past experience, but contrary to company practice, the RCT attempted to troubleshoot the instrument by replacing the fuse with one from a known working model. When the sampler again failed to start, the RCT attempted to remove the fuse, neglecting to disconnect the instrument from the electrical supply. He experiencing a mild tingling sensation and reported to the site nurse for evaluation.
The RCT had been trained on electrical safety and knew that the correct response for fixing broken equipment was to tag the equipment and generate an �Action Request.� He did not recognize that troubleshooting was not authorized when he attempted to replace the fuse.
Analysis
Neither the air sampling procedure nor the manufacturer�s manual effectively communicated the expectations related to troubleshooting the equipment.
Subsequent investigation discovered obvious scorching, melting and separation from the termination at the instrument switch which would not have been �fixed� by a replacement fuse.
Recommended Actions
Below are the consequences of the above event. They are provided for information and discussion purposes only.
Immediately after the event, the portable air sampler was tagged out of service.
The following actions were then performed:
Inspection of the unit, by an electrical subject matter expert and an instrumentation and calibration technician. It was found that the unit had incurred an electrical fault resulting from less than adequate conductor terminations originally installation by the manufacturer.
An extent of condition review was performed on all portable air samplers. This review identified five others units that showed evidence of excessive heat buildup and/or arcing. With concurrence from the manufacturer, faulty conductor terminations on multiple units were identified and corrected.
Periodic preventive maintenance has been scheduled to visually examine the interior electrical components of portable air samplers.
JLab Preventive Measures
Jefferson Lab�s Electrical Safety Program specifically states that it is the responsibility of everyone to Request an inspection from a qualified electrical inspector.
� Be aware of electrical hazards.
� Perform work using electrical safe work practices.
� Report electrical hazards to your Supervisor.
� Submit a Facilities Management Work Request if new, repair, or maintenance electrical work.
� Report cases of electric shock to Jefferson Lab Occupational Medicine Department.
� Request an electrical hazard evaluation if a piece of electrical equipment malfunctions.
Comments
7/14/2015 3:16:27 PM by Bailey, Mary Jo
Submitted to those current in :
SAF104: LOCK, TAG, AND TRY
SAF607: HAND TOOLS & LADDER SAFETY
SAF603A: ELECTRICAL SAFETY AWARENESS
Summary Lesson ID: 896
Status: OK
Doc ID: 2015-JLAB-896
Priority: Info
Safety Related: YES
Originator: Bailey, Mary Jo
Issued: 7/14/2015 3:12:25 PM
Approved By: Bailey, Mary Jo
Approved On: 7/14/2015 3:16:27 PM
Source: DOECRD
Location: OTHER
Cost Savings:
Contact: Brenda Kirkes, Nuclear Waste Partnership, LLC, 575.234.8236
Queued Emails: 0
Sent Emails: 0
Viewings: 2 times Attachments
* DOE - Mild Shock.pdf
Hazard Issues
* Electricity
* Tools - Machine & Portable
Skills
* SAF104: LOCK, TAG, AND TRY
* SAF607: HAND TOOLS & LADDER SAFETY
* SAF603A: ELECTRICAL SAFETY AWARENESS
Distribution/Notification
* *Division Safety Officers (DSOs)
* *Safety Wardens
* *DOE Notification
* *ESH&Q Liaisons
Do you have a lesson learned you would like to contribute? Contact the Lesson Learned Coordinator .
More information about the Hallb-engineering
mailing list