[Hallb-solenoid] Progress of interlock checkout List.

Nicholas Sandoval sandoval at jlab.org
Wed Oct 5 17:20:03 EDT 2016


Hi Pablo,

Please contact me as soon as you discover nomenclature related to the document P027 that would hold up progress.  Clarification in most cases can be handled immediately over the phone.

If you have any other questions related to completing the document or other hardware issues and cannot find immediate help in the Hall you can always contact me at: x7489, x6506, or 540-907-2637 (try in that order)

Thanks and Best Regards,

Nick

----- Original Message -----
From: "Pablo Campero Rojas" <campero at jlab.org>
To: "Ruben Fair" <rfair at jlab.org>
Cc: hallb-solenoid at jlab.org
Sent: Wednesday, October 5, 2016 4:48:33 PM
Subject: [Hallb-solenoid] Progress of interlock checkout List.

Dear Ruben, 

We could not completed any test this afternoon, for the followings reasons: 
1. Waiting for SOE relays wiring to be finished to allow the dump contactor open (MPS) 
2. Waiting for voltage injection test to be finished, it cause VT Cable interlock. So we can not verify all interlocks clear, step which applies to almost all the remain interlocks test. 
3. Waiting for clarification from Nick on procedure for comparator test. 
The total tasks completed is still 16 of 51. 

Pablo Campero 

_______________________________________________
Hallb-solenoid mailing list
Hallb-solenoid at jlab.org
https://mailman.jlab.org/mailman/listinfo/hallb-solenoid


More information about the Hallb-solenoid mailing list