Dear Collaborators,

    Accelerator is down due CHL recovering after CHL transformer fail :
    -First new transformer installed, warmed up and energized. Load test done successfully. 400 Amps load is stable.
    -Second transformer (old one) will be demontaged today.
    -Second new transformer will be set and hook up tomorrow (Saturday March 17). Weather (rain showers) could affect
     setting and probably could shift schedule a little bit
    -CHL will be on full power at Sunday March 18
    -CHL 2K pump down will happen Sunday or Monday morning depending on how things going
    -Beam restoration will occur Wednesday March 21
    -All experimental halls will be staffed by March 23 for high current tests
    -Physics will start March 26-28

     Shifts cancelled till March 21 Day shift.
     Please sign up for later shifts, we have a lot of empty slots. 

     Monday morning news from MCC will be critical in terms of preparation HallC to the beam.  
     So please participate in RC meeting at Monday. 
     

 We will meet Monday March 19 at 1:30 p.m. in the conference room located on the second floor of the counting house.
 Remote participation will be possible via Blue Jeans (Meeting ID: 543903672). You can join via:

browser:
https://bluejeans.com/543903672

phone:

(888) 240-2560 (US toll free)
list of international numbers: https://bluejeans.com/numbers

   
   
    
    

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3544940
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20180316/d64d8673/attachment.html>


More information about the Hallc_running mailing list