[Hallc_running] [New Logentry] RC Update -- Hall lockup on Thursday Swing (Beam on Sat?)
brads at jlab.org
brads at jlab.org
Tue Jul 28 13:30:03 EDT 2020
Logentry Text:
--
So I guess things are going well in Accelerator and we've been asked to be ready for beam by Saturday Day shift.
The current plan is to take the Hall to Controlled Access on Thursday Swing. That means we should have our Hall, beamline, detector (and target) checklists done by then.
Any tools, notebooks, hardware, etc should be cleaned up and removed from the Hall over the next few days. (As always, if you're not 100% sure something has not seen beam, then make sure RadCon surveys it first.)
I've reactivated the 3 shifts from Saturday Day, Sat Swing, and Sun Owl in the shift schedule for now (following shifts were already active).
** We do need a SL for Sunday OWL **
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3817435
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20200728/3c181f23/attachment.html>
More information about the Hallc_running
mailing list