[Halld-jlab] Hall D Staff Meeting Notes, April 23, 2012
Mark M. Ito
marki at jlab.org
Mon Apr 23 17:18:36 EDT 2012
Find the notes at
https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_April_23,_2012
and below.
_____
Private:Hall D Staff Meeting, April 23, 2012
Present: John Domingo, Hovanes Egiyan, Mark Ito, Vanik Kakoyan, David
Lawrence, John Leckey, Lubomir Pentchev, Elton Smith (chair), Sascha
Somov, Simon Taylor, Tim Whitlatch, Elliott Wolin, Glenn Young, Beni
Zihlmann
Summer Projects, Tim
* solenoid
+ installing yoke, baffle, axial support
+ paint the solenoid
+ solenoid platform
+ power supply for solenoid
+ pick-up coils
* grounding cables
* cable trays
* install pair spectrometer magnet, vacuum box
* active collimator, install
* installing primary collimator, testing
* downstream FCAL platform/carriage
* FCAL block stacking
* BCAL rails mounted to solenoid
* BCAL light-guides, mount on wedges
* install DAQ system in ESB for BCAL tests
* tagger building
+ LCW manifolds
+ assemble gantry crane
+ stands
* collimator cave shielding
* air pressure lines
Student Support Requests, All
* Elton: from Regina, mid-July, one undergrad and one grad
* Sascha: from UNCW, two students last year, at least one this year
* Tim: 3 engineering students: 2 SULI, 1 co-op
+ one on completing cooling system for BCAL
+ one doing same for FDC
+ one on target design
* JLab SULI student with Elton and David, start beginning of June,
BCAL testing
* CNU students, Ed agrees to send one, no shortage of projects, Dave
and Elliott
* Vladimir coming from MePHI
* Lubomir requested CV's of the students to help decide where they
should be deployed
* Lubomir may have jobs in EEL 126, FDC testing
* Elliott may have some irregular jobs
* Elliott points out that they need somewhere to sit. Need computers
as well.
Open House, David
* one month from open house
* will get another BCAL module
* all volunteer slots filled up
* plenty of volunteers now
No More Oxygen in the FDC, Lubomir
* 75 ppm in one production cell
+ Viton o-rings and vacuum grease on top, glue on bottom
* expect different problems with quenching
+ O[2] a good quenching gas
* next go for three more cells
Software Review, David
* no charge yet
Upgrade Workshop, Elton
* a week from Wednesday
* internal discussions of ideas
+ calorimeter
+ RICH
+ level-3 farm
--
Mark M. Ito
Jefferson Lab (www.jlab.org)
(757)269-5295
More information about the Halld-jlab
mailing list