[Halld-jlab] Hall D Staff Meeting Notes, January 26, 2015
Mark Ito
marki at jlab.org
Tue Jan 27 12:18:06 EST 2015
People,
Find the notes below and at
https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_January_26,_2015
.
-- Mark
__________________________________________________
Private:Hall D Staff Meeting, January 26, 2015
Present: Present: Fernando Barbosa, Eugene Chudakov (chair), Mark
Dalton, Alexandre Deur, Hovanes Egiyan, Sergey Furletov, Mark Ito, Bert
Manzlak, Paul Mattione, Sergey Pozdniakov, Sascha Somov, Simon Taylor,
Beni Zihlmann
Announcements, Eugene
* Timesheets from last October require review due to hours moved from
ops to 12 GeV. Please respond to notifications.
* conference travel
o last year: invited talks only
o if interested in giving invited or contributed, see Eugene
o there is an accelerator conference coming up in Richmond, if
interested let Eugene know
* budget
o more info at Feb. 3 DOE briefing
o Fall run: 6 weeks with 25% uptime, a revised schedule coming soon
* taking over Yi's former responsibilities
o solenoid controls: Beni
o PDL: Beni
o PWA work with Carlos: Paul and Justin should attend meetings,
Simon and Mark should continue to do so
o DIRC:
+ new photo-detectors from Argonne a prospective project
+ Justin can work on Hall B solution
* preparations for run
o liquid hydrogen target
+ hazard analysis from Tim
+ target group will operate target
o goniometer hazard analysis needed
+ diamond heating
+ high beam current protection
+ measures to keep frame out of the beam
o want to increase maximum electron beam current to 1 microamp
o want to increase solenoid current to 1300 A (to 1350 A for
hysteresis)
o Alexandre will start as run coordinator, David will take over,
Mark I. will backup
Electronics, Fernando
* HVBs for CDC all installed, finishing cabling
o will start powering HV and LV as test
o then connect signal cables, look at signals
o then turn on gas system
o run with pulser in FADC, scan all channels
* cables for polarimeter
o little advance notice
o 32 + 24 coax cables needed, will exhaust spares on hand
o ASU will bring power supply
* master oscillator
o tagger and hall fibers in
o next chassis will come from Accel.
o cables being ordered, from Accel. chassis to MO module
o MO module working, USM design
+ Alam Toro working on firmware, can run without it if pressed
+ can step down by factor 128
+ for F1, under 5 MHz needed
* F125s: 25 modules came in, only 5% failure rate
Run Planning, Alexandre
* will use same structure for plan as for Fall
* times, goals similar
* detailed plan being put together
o so far: target, electron beam, photon beam
o major items:
1. target
2. diamond
3. 1300 A
o items of note:
1. DAQ, block mode, 20 kHz
2. RF timing
3. TAC
4. polarimeter
o other items:
1. complete detector calibration and alignment
2. trigger optimization
3. pair spectrometer trigger
4. suppress FCAL noise
5. beam stability and fast feed-back
6. monitoring transmission through collimators
Safety, Burt
* will to do evaluation of mandatory hearing protection zone on
platform next Wed.
o will break vacuum window on pair spectrometer vacuum box
o noise level will be measured
o request comes from engineering group
MCP DIRC Read-Out, Beni
* Carl Zorn will take lead on project
* Beni will supervise student and post-doc
* Post-doc may need laser training
Science Magazine and GlueX, Fernando
* article in Science on JLab featured picture of CDC
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_January_26,_2015"
* This page was last modified on 27 January 2015, at 17:10.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/halld-jlab/attachments/20150127/aa930b6c/attachment.html
More information about the Halld-jlab
mailing list