[Halld-offline] Calibration job update

Sean Dobbs s-dobbs at northwestern.edu
Wed Apr 6 18:51:43 EDT 2016


Dear all,

The first set of calibration jobs, running over the 5mm collimator data
taken before the long accelerator down time have finished.
The results can be found at
 /volatile/halld/home/gxproj3/calib_jobs/GlueX-CalibRun-2016-03-18
and the skim files at
 /cache/halld/home/gxproj3/calib/GlueX-CalibRun-2016-03-18

As a reminder, we are creating skims for pi0 calibration, TOF calibration,
and for gamma p -> p pi0 events.

The second set of jobs, covering the 3.4 mm collimator data taken recently
have been started.  The first two passes have finished, and the final step
is underway, with skim files being created.
The results can be found at
 /volatile/halld/home/gxproj3/calib_jobs/GlueX-CalibRun-2016-04-04
and the skim files at
 /cache/halld/home/gxproj3/calib/GlueX-CalibRun-2016-04-04


Cheers,
Sean
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-offline/attachments/20160406/3425732c/attachment.html>


More information about the Halld-offline mailing list