GlueX Start Counter Meeting, June 2, 2011
Minutes
Present:
* FIU: Werner Boeglin, Lei Guo
* JLab: Mark Ito (chair), Sascha Somov, Beni Zihlmann
Fiber Order
Lei contacted Kuraray and ordered 1 × 1 mm fibers. They have arrived.
They will be clamped into a shape that can be attached to a
scintillator.
Scintillator Order
The scintillator will arrive from Plastic Craft by June 13.
Resolution Studies
Werner is doing measurements with the SiPM array he has to try to
understand the source of the timing variance. Using a leading-edge
discriminator he is trying to predict the resolution one should expect
from the width of the pedestal (noise), and the measured rise time of
signals. He corrects for time walk in software. So far he sees
resolution consistent with noise driving the observed resolution.
SiPM's for FIU
The SiPM's that [36]Sascha ordered some time ago have arrived, again,
some time ago. Fernando has made pre-amps for single 3 × 3 mm cells of
two varieties, one with a gain of 35, the other with 70. Measurements
in Vitaly Baturin's set-up look good. Sascha is trying to create our
own set-up so we can do the tests ourselves.
Werner is anxious to test any of the new SiPM configurations we can get
to him. So far he has only been working with an array with an older
version of the pre-amp. He will be here next week and will talk to
Fernando about getting something to take back to Miami.
Segmentation
Werner is still considering segmentation of 30 counters rather than the
nominal 40. If the thickness is kept constant then this might help
light output since the higher aspect ratio of the cross-sectional area
has more perimeter on the faces relative to the edges. Previous studies
showed that a large part of the light loss was coming from the edges of
the scintillator.
MOU Status
* Sent latest version to Allison on May 5.
* Got comments from Glenn Young on May 17.
* Sent Glenn's comments to Werner today.
* Will incorporate Glenn's comments and re-submit to Allison.
We agreed that we should not wait for the MOU to be signed before
starting work on the construction contract. Werner mentioned that he
does not have easy access to a designer at FIU. As such, the drawings
will be done here as they have been done for other detectors.
Retrieved from
"http://www.jlab.org/Hall-D/software/wiki/index.php/GlueX_Start_Counter_Meeting%2C_June_2%2C_2011"
References
36. https://mailman.jlab.org/pipermail/halld-pid/2011-April/000159.html
More information about the Halld-pid
mailing list