[Halld-pid] Start Counter Meeting Minutes, January 24, 2013
Fernando J Barbosa
barbosa at jlab.org
Wed Jan 30 18:03:24 EST 2013
Mark, Werner,
We have all the cables for installation, which is scheduled to occur in
late June to early July. Note, however, that the readout w/ SiPMs is
scheduled to be available by the end of July.
We need to minimize any outside requests for equipment to be shipped
from JLab due to installation schedules. I also heard that shipping of
any equipment out of JLab now needs to be approved by DOE. Please check
on this as soon as possible and develop a plan/schedule, considering
installation in the hall.
Best regards,
Fernando
On 1/29/2013 10:30 AM, Mark M. Ito wrote:
> Find the minutes at
> https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_January_24,_2013#MinutesGlueX
> and below.
>
> ___
>
> Start Counter Meeting, January 24, 2013
> Minutes
>
> Present:
> * FIU: Werner Boeglin, Puneet Khetarpal, Eric Pooser
> * JLab: Chuck Hutton, Mark Ito (chair)
>
> Contract
>
> The proposal from FIU is past due. On the other hand, Mark has
> exchanged email with Jarrod Fitzpatrick, and this situation seems less
> than dire. Werner thinks that he can come up with a draft Procedures
> and QA plan by Monday. Mark agreed to review the plan.
>
> Counter Construction
>
> Eric is in contact with Chuck Hurlbut at Eljen and Robert McNeal (at
> McNeal) and is getting quotes on their respective construction steps.
> The cost from McNeal should be about the same as for the previous
> prototypes.
>
> Werner asked about cables for testing the counters. Mark told us that
> his understanding is that JLab will supply the cables. Mark will
> confirm that with Fernando. We decided that we would make a tentative
> plan to try to test all thirty counters at once at FIU. That will drive
> plans for lending electronics and for manufacturing cables in advance
> of installation in the Hall.
>
> Eric reported that Eljen is suggesting that we use EJ-200 rather than
> the EJ-212 we had planned for originally. We will order five counters
> initially, with height and width of 3 mm × 30 mm before machining.
> Including the cost of practice runs, it should come out to about $200
> per counter. Eljen says that once the order has been placed, the
> counters can be manufactured in a matter of days.
>
> Chuck Hutton will ask around and see how folks at the Lab have made
> sure that vendors adhere to the required shipping standards.
>
> Assembly Drawings
>
> We looked at a set of drawings Chuck has done with the final dimensions
> of the start counter support structure.
> * [17]Foam Cone Assembly
> * [18]Inner Foam Cone
> * [19]Foam Cone Ring
>
> Retrieved from
> "https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_January_24,_2013"
>
> References
>
> 17. https://halldweb1.jlab.org/talks/2013-1Q/1001.pdf
> 18. https://halldweb1.jlab.org/talks/2013-1Q/2001.pdf
> 19. https://halldweb1.jlab.org/talks/2013-1Q/2002.pdf
>
> _______________________________________________
> Halld-pid mailing list
> Halld-pid at jlab.org
> https://mailman.jlab.org/mailman/listinfo/halld-pid
-------------- next part --------------
A non-text attachment was scrubbed...
Name: barbosa.vcf
Type: text/x-vcard
Size: 265 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/halld-pid/attachments/20130130/22bdafa9/attachment-0002.vcf>
More information about the Halld-pid
mailing list