[Halld-tagger] Hall D radiator target plans/schedule?
Hovane Egiyan
hovanes.egiyan at gmail.com
Wed Sep 25 22:18:25 EDT 2013
Tim is already making an insertion device which will allow us to have
at least 3 targets near the goniometer (10^-4,10^-3, 10^-4). With some
modifications
to the ladder design, we can have four targets (if you think that we
will need four amorphous
targets, then please let Tim know very soon). These will be amorphous
radiators,
not diamond crystals for coherent bremsstrahlung , and according to the
last version of
the schedule that I have seen, it is not unrealistic to have them by
spring of 2014. With these
targets we can attempt to tune the photon beam into the hall and use the
lessons in the fall, if
we get any beam time on this targets.
I agree that we need to finalize the number of the targets and even
their thicknesses at this
collaborations meeting.
Hovanes.
On 9/24/2013 6:26 PM, Richard Jones wrote:
> Hello Todd,
>
> Good question, to which I don't have a ready-made answer. I could
> shoot from the hip, but would prefer to raise it at the collaboration
> meeting and get an agreed-upon list to submit to you. Does that make
> sense? I think that Hovanes has already been thinking about that
> question, but there are others who will also want to have input.
>
> -Richard J.
>
>
> On Mon, Sep 23, 2013 at 12:17 PM, Todd Satogata <satogata at jlab.org
> <mailto:satogata at jlab.org>> wrote:
>
> Hi Richard,
>
> One thing that came up in a recent meeting with our safety guys is
> a question
> about plans for foils or other possible targets in the goniometer
> over the
> next couple of runs (during FY14). Could you let me know what
> targets you
> plan to have in place, if any, on what timescale, or let me know
> who the
> best person would be to ask about these sorts of things so I can
> forward
> it along to Kelly? I definitely know that we intend to establish first
> beam on the tagger enclosure dump in the spring, and that there is
> some
> interest in looking at backgrounds and downstream effects on any
> detectors
> in the hall, but don't know if there is a plan to install any foils or
> other targets. Could you also let me know when you expect to have
> first
> radiator and photons delivered? Many thanks!
>
> -Todd
>
> --------------+---------------------------+----------------+------------------
> Todd Satogata | CASA Group, Jefferson Lab | (757) 269-6281
> <tel:%28757%29%20269-6281> | satogata at jlab.org
> <mailto:satogata at jlab.org>
> --------------+---------------------------+----------------+------------------
>
>
>
>
> _______________________________________________
> Halld-tagger mailing list
> Halld-tagger at jlab.org
> https://mailman.jlab.org/mailman/listinfo/halld-tagger
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/halld-tagger/attachments/20130925/493b1e94/attachment.html
More information about the Halld-tagger
mailing list