[Halld-tracking-hw] CDC components
Curtis A. Meyer
cmeyer at ernest.phys.cmu.edu
Wed Jun 2 15:17:18 EDT 2010
Hi Tim -
yes, please have them sent directly to us and we will forward some to
you. That will be
a big help to have them at the end of June.
curtis
On 6/2/10 2:52 PM, Tim Whitlatch wrote:
> Hi Curtis,
>
> The plastic part samples should be here by June 16. With a quick
> turnaround, they can have the final parts shipped by the end of June
> (the entire batch takes 6 days to produce so a partial shipment will
> not buy us much). We can have them shipped directly to you if that
> helps? You can send some of the parts to JLAB to look over.
>
> Tim
>
> Curtis A. Meyer wrote:
>> If we would get a partial shipment when they start production, that
>> would help.
>>
>> thanks -- Curtis
>> On 6/1/10 1:13 PM, Tim Whitlatch wrote:
>>> Hi Curtis,
>>>
>>> All 3 plastic pieces are run in the same mold. They will make
>>> samples again in a week or two. We can check them quickly and they
>>> will run the production quantities. I will be surprised if this can
>>> all be done before July.
>>> I will call them and see what we can do to speed this up.
>>>
>>> Tim
>>>
>>> Curtis A. Meyer wrote:
>>>> Hi Tim -
>>>>
>>>> is there any way to speed up the plastic donuts and
>>>> feedthroughs? They all need to be
>>>> checked before we can start putting straws in and any headway we
>>>> can make on that
>>>> would be very helpful. We do not need the pin holders (which we
>>>> changed), but the other
>>>> two parts (that were fine) would be extremely helpful to get this
>>>> month.
>>>>
>>>> thanks -- Curtis
>>>>
>>>>
>>>> On 6/1/10 10:17 AM, Tim Whitlatch wrote:
>>>>> Hi Naomi,
>>>>>
>>>>> We are sending approx. 9000 crimp pins up your way today. We had
>>>>> received them from Medelec last week.
>>>>> The ones we checked fit the plastic inserts very nicely. A little
>>>>> hard threading the tungsten wire through, probably need 10x
>>>>> magnification or something.
>>>>> The plastic components should be your way by Mid July.
>>>>> The next batch of straws should also be your way by July. Maybe we
>>>>> should send someone to Lamina to check instead of wasting the time
>>>>> for them to send the samples to the US?
>>>>> The inner skin and support rings should be your way before the end
>>>>> of this month (June).
>>>>>
>>>>> Cheers,
>>>>>
>>>>> Tim
>>>>>
>>>>> Naomi Jarvis wrote:
>>>>>> Good morning!
>>>>>>
>>>>>> Our new technician - Amy Woodhall - started work this morning and
>>>>>> is busy reaming the C endplate holes... we also have 3 students
>>>>>> here and need to do some forward planning... please could you
>>>>>> give me a heads up as to when we can expect to see the plastic
>>>>>> components, next batch of straws and the inner shell? A rough
>>>>>> idea (likely month) would be helpful if you do not know more
>>>>>> exactly, I imagine the plastic cpts should not be too long.
>>>>>>
>>>>>> Thanks,
>>>>>>
>>>>>> Naomi.
>>>>>
>>>>>
>>>>> _______________________________________________
>>>>> Halld-tracking-hw mailing list
>>>>> Halld-tracking-hw at jlab.org
>>>>> https://mailman.jlab.org/mailman/listinfo/halld-tracking-hw
>>>>
>>>>
>>>> --
>>>> Prof. Curtis A. Meyer Department of Physics
>>>> Phone: (412) 268-2745 Carnegie Mellon University
>>>> Fax: (412) 681-0648 Pittsburgh PA 15213-3890
>>>> cmeyer at ernest.phys.cmu.edu http://www.curtismeyer.com/
>>>>
>>>>
>>
>>
>> --
>> Prof. Curtis A. Meyer Department of Physics
>> Phone: (412) 268-2745 Carnegie Mellon University
>> Fax: (412) 681-0648 Pittsburgh PA 15213-3890
>> cmeyer at ernest.phys.cmu.edu http://www.curtismeyer.com/
>>
>>
--
Prof. Curtis A. Meyer Department of Physics
Phone: (412) 268-2745 Carnegie Mellon University
Fax: (412) 681-0648 Pittsburgh PA 15213-3890
cmeyer at ernest.phys.cmu.edu http://www.curtismeyer.com/
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/halld-tracking-hw/attachments/20100602/cdf75fa6/attachment.html
More information about the Halld-tracking-hw
mailing list