Comments have been incorporated. See highlighted text below in this email chain for changes made to the procedure. The updated procedure PLACLN-PR-VSA-CAV-MODE has been added to the Ready for Approvals folder. Please delete the current / disapproved version, move the updated procedure to the Approvals folder, and send the updated procedure version out for approval.
Thank you,
Tiffany Ganey
From: Allen Samuels <samuels at jlab.org>
Sent: Tuesday, April 27, 2021 4:02 PM
To: Tiffany Ganey <ganey at jlab.org>
Cc: pansophy <pansophy at jlab.org>
Subject: FW: New DocuShare document routing task (Step 1 Completion): PLACLN-PR-VSA-CAV-MODE.docx
Tiffany,
Tom powers has disapproved PLACLN-PR-VSA-CAV-MODE. Please address his requests, and upload the revised version to ready for approvals. I will route it from there and we can move forward.
Thank you for your time,
Allen Samuels
From: DocuShare Workflow <docushare at jlab.org<mailto:docushare at jlab.org>>
Sent: Tuesday, April 27, 2021 3:39 PM
To: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Subject: New DocuShare document routing task (Step 1 Completion): PLACLN-PR-VSA-CAV-MODE.docx
You have a new DocuShare document routing task:
Subject: PLACLN-PR-VSA-CAV-MODE.docx
Date: 04/27/2021 15:38:44
Updated with Tiffany's revisions
Step 1 Completion:
Tiffany Ganey, 04/09/2021 12:25:19 Approved:
Natalie Brock, 04/09/2021 14:32:13 Approved:
Tom Powers, 04/27/2021 15:38:44 Disapproved:
General warnings. The VTA/VSA is also a radiation area when high power tests are being preformed. In addition to flip signs indicating a change in state, the megenta beacons on each shield lid are an indication that high power operation is enabled. Individuals who have not approved to be in the VTA/VSA during high power operation as per the RWP are required to leave the area during high power testing.
New step 2.2 added and subsequent steps renumbered: The VTA / VSA is a radiation area when high power tests are being performed. In addition to flip signs indicating a change in state, the magenta beacons each shield lid are an indication that high power operation is enabled. Individuals who are not approved to be in the VTA / VSA during high power operation as per the VTA RWP are required to leave the area during high power testing.
Step 7.3. There is a bug in at least one of the NAs. If all of the selections are blank choose the cal kit 85514A then choose cal kit 85515A. {I do not know what it works but it does and I reported it to Keysight.}
Second bullet of 7.3 revised to add NOTE.
On the next screen, select:
· Connector: Type N
· Cal Kit: 85515A
NOTE: If all of the selections are blank, choose the Cal Kit 85514A and then choose the Cal Kit 85515A.
· Port 1 check box yes, select Female
· Port 2 check box no
· Cal Type: OSL
Step 7.7 if you interrupt the calibration process, restart it or do one of the standards multiple times the percent complete will likely be in error it is better to look for the small check marks above the green open short load boxes.
New step 7.8 added and subsequent steps renumbered: Verify that the calibration process was completed correctly by verifying that there is a check mark for each of the Open, Short, and Load boxes. If any boxes are missing a check mark, perform that portion of the calibration process before continuing.
Will be approved after the above comments are addressed.
Tony Reilly, 04/12/2021 11:35:16 Approved:
To view your pending document routing tasks, click on the link below to login to DocuShare:
https://jlabdoc.jlab.org/docushare/dsweb/routing/routing_email.jsp?url=report_base.jsp&reportType=ForApprovalCompletion&routingSlipRequestID=17432¬ifyID=17443&workFlowJobName=17432
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210428/c383defb/attachment-0001.html>
More information about the Pansophy
mailing list