[PEPPo] installation update
Joe Grames
grames at jlab.org
Wed Jun 1 22:43:29 EDT 2011
Dear PEPPo Collaborator:
Activities are already underway in preparation for the installation of
the experimental apparatus later this summer. This means work is going
on both at surface level in the Injector Service Building (ISB) and
tunnel level in the injector region of the accelerator enclosure. You
will begin to receive regular installation updates about new or on-going
activities. You should read these and ask questions if you are
unclear. Presently, a handful of us are in a position to be working in
these areas, but at the summer progresses many more collaborators will
be in this position.
1. _*Cable Penetrations Opened*_ - Two cable-way penetrations which
connect the ISB to the tunnel at locations IN02B23 & IN02B24 were opened
today, meaning the stones which fill the penetration have been dumped
out of each preparation in preparation for pulling new cables (HV,
signal, magnet, etc) through them. For the duration these penetrations
are open the work area around and above the racks is elevated from ODH-0
to ODH-1. For those who already have Oxygen Deficiency Hazard (ODH)
training, this means the two-person buddy-rule is in effect. Signs have
been placed to define the area and an ODH monitor has been placed above
the region, and will be activated Thursday morning 6/2. As usual, if
the ODH system ever goes into alarm (blue beacon & horn) you must exit
the building. If this doesn't make sense to you then you probably
haven't taken ODH training, so you shouldn't yet be working in this area.
2. _*Work Area Personal Protective Equipment (PPE)*_ - The injector
accelerator enclosure downstream of the cryounit (plastic curtain) is
now an installation area. Personnel in this area should wear closed
shoes (no sandals) and pants (no shorts). In addition, it is
recommended that those working below the open penetrations wear safety
glasses and hardhats as small stones and or materials can drop from the
surface level to the tunnel level.
3. _*Injector Walkway Installation Planned Next Week June 6th*_ - The
new injector platform at the injector accelerator enclosure is on track
for installation next week and will last 2-3 days. During the
installation please pay attention to any posted signs. The task
includes a significant amount of drilling and hammering, with some dust
and noise. During these activities avoid the work area if possible.
As always, if questions/issues arise you can contact me on my cell
757-344-0188.
Joe
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/peppo/attachments/20110601/11070094/attachment.html
More information about the PEPPo
mailing list