Items which are within the beam enclosure while beam is present must be
surveyed prior to removal. However, those upstream of the injector gate
may be removed without the survey because the electron beam energy there
(~6.3 MeV) remains below threshold for activation. This is particularly
useful for tools, electronics, cables, etc. As we increase the injector
beam energy towards 8 MeV for PEPPo and Mott experiments we will
re-evaluate with RadCon this condition.