[PEPPo] Daily RC Report 5/23

Joe Grames grames at jlab.org
Wed May 23 18:34:17 EDT 2012


*Daily RC Report 5/23:*
The survey/alignment group completed survey measurements of the injector 
and PEPPo components today.  The horizontal centerlines of components 
are in good alignment, as well as the fiducalized polarimeter axis.  
There is a small negative pitch of the spectrometer and region 3 beam 
line likely resulting from cantilevered region load resulting in exit 
window low ~4mm.  Consequently, we're planning to re-align the pitch on 
Thursday morning.  Otherwise, all work is going per plan.

*Noteworthy items:*
1. The clothing (PPE) rules requires that people working in the tunnel 
and service buildings have closed toed shoes and long pants.
2. Erica & Riad will provide the DAQ/ANALYSIS training on Thursday at 
9:30am in MCC conference room.

*Next 24 hours:*

    _Wednesday, 5/23 - SWING_

        * Compton and annihilation detector source calibrations

    _Thursday, 5/24 - OWL_

        * No planned work

    _Thursday, 5/24 - DAY_

        * 0800 Complete alignment of region 3 and Compton
        * 1200 If alignment complete opportunities for detector checkout
        * 1500 Sweeps of INJ/NL for HCO begin

    _Thursday, 5/24 - SWING_

        * Complete configuration for detector and shielding for
          commissioning
        *


-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/peppo/attachments/20120523/282d08c9/attachment.html 


More information about the PEPPo mailing list